Vantage MXP1 Milan Data Center Campus

Melegnano, Milan, Lombardy, ItalyPartially operational
Evidence
Planned critical IT
64 MW
Updated
Oct 28, 2026

Vantage MXP1 Milan Data Center Campus, also known as Vantage MXP1 Milan I, is a data center project in Melegnano, Milan, Lombardy, IT associated with Vantage Data Centers. 30-acre campus; four data centers at full development; 517,000 square feet; 64 MW critical IT load. 220 kV onsite substation, multiple utility feeds, closed-loop chilled-water cooling and carrier-neutral connectivity. 64 MW is the operator’s campus specification and is consistent with the 96 MW combined Milan portfolio after MXP2. A 32 MW building-level figure in a translated sheet is retained as phase context, not substituted for the campus boundary.

Capacity

Reported capacity

Design

64 MW

Source

Reported capacity

Planned / design or future potential

64 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionPartially operational

64 MW is the operator’s campus specification and is consistent with the 96 MW combined Milan portfolio after MXP2. A 32 MW building-level figure in a translated sheet is retained as phase context, not substituted for the campus boundary.

Participants

Vantage Data Centers

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

Vantage MXP1 Milan I | Melegnano, Milan | Lombardy | IT

Source

Location context

Actual

Vantage MXP1 Milan I | Melegnano, Milan | Lombardy | IT

Source

Location context

Actual

Melegnano, Milan, Lombardy, IT

Source

Development detail

Actual

30-Acre campus; four data centers at full development; 517,000 square feet; 64 MW critical IT load.

Source

Additional project facts

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

Vantage Data Centers publishes 64 MW of critical IT capacity for this record boundary.

Source

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

64 MW is the operator’s campus specification and is consistent with the 96 MW combined Milan portfolio after MXP2. A 32 MW building level figure in a translated sheet is retained as phase context, not substituted for the campus boundary.

Source

Project boundary

Actual

Vantage MXP1 Milan I

Source

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

64 MW is the operator’s campus specification and is consistent with the 96 MW combined Milan portfolio after MXP2. A 32 MW building level figure in a translated sheet is retained as phase context, not substituted for the campus boundary.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Energized

220 kV onsite substation, multiple utility feeds, closed-loop chilled-water cooling and carrier-neutral connectivity.

Cooling system

Operational

Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (1)
Vantage MXP2 Milan Data Center Campus

Under construction · Castelletto, Milan, Lombardy, Italy

Shared participant: Vantage Data Centers · Same market: Lombardy, Italy