Data center siteSite record

Vantage Lighthouse Port Washington AI Data Center Campus

Port Washington, Wisconsin, United StatesUnder construction
Capacity
902 MW
Planned critical IT
Lead participant
Vantage Data Centers
Developer
Last updated
Aug 28, 2026
Most recent public record update

About Vantage Lighthouse Port Washington AI Data Center Campus

Vantage Lighthouse Port Washington AI Data Center Campus, also known as Vantage Lighthouse Campus, is a data center project in Port Washington, WI, US associated with Vantage Data Centers. 672-acre AI campus; four planned data centers; 902 MW critical IT load; approximately 2.5 million square feet. Large AI-optimized campus designed as four buildings with dedicated high-capacity electrical and advanced cooling systems. 902 MW is the operator-published future facility or full-build design boundary.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load902 MWDesign · Vantage Lighthouse Port Washington AI Data Center Campus
Future Potential902 MWDesign · Vantage Lighthouse Port Washington AI Data Center Campus

Development

1 phases · 2 milestones
Development, permitting and phased deliveryUnder Construction

902 MW is the operator-published future facility or full-build design boundary. It is not operating IT load.

Dec 1, 2025
Construction began on Project Lighthouse
Completed
Dec 31, 2028
Operator and OSHA documents schedule campus completion during 2028
Forecast

Infrastructure

Electric GridPlanned Or Represented

Large AI-optimized campus designed as four buildings with dedicated high-capacity electrical and advanced cooling systems.

Cooling SystemPlanned Or Represented

Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.

WaterPlanned Or Represented

16 inch main

City and state records describe a 4.2-mile water-main extension serving the site.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Cooling & water: 2

Facts & sources

Published claims and their source links.

13 facts
Location Context
Vantage Lighthouse Campus | Port Washington | WI | US
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
902 MW
Design
Capacity Basis
Vantage Data Centers publishes 902 MW of critical IT capacity for this record boundary.
Actual
Location Context
Vantage Lighthouse Campus | Port Washington | WI | US
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
902 MW
Design
Capacity Basis
902 MW is the operator published future facility or full build design boundary.
Actual
Site Area
672 acres
Actual
Building Count
4
Design
Building Area
2,500,000 square feet
Design
Scheduled Completion
2028
Forecast
Owned Land
1,644 acres
Actual