Evidence
Planned critical IT
13 MW
Updated
Oct 28, 2026
Utility
CLP Power Hong Kong

Vantage HKG2 Fo Tan Data Center, also known as Vantage HKG2 Fo Tan, is a data center project in Fo Tan, Hong Kong, HK associated with Vantage Data Centers. 13-story Tier III facility; 10 data modules; 185,000 square feet; 13 MW critical IT load. China Light & Power feeds, N+1 block-redundant electrical systems, modular chillers and carrier-neutral connectivity.

Capacity

Reported capacity

Design

13 MW

Source

Reported capacity

Planned / design or future potential

13 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionOperational

13 MW is the operator-published facility or campus design boundary.

Participants

Vantage Data Centers

Developer

Sources by role
Developer (1)
Other participants (1)
CLP Power Hong Kong

Utility provider

Sources by role
Utility provider (1)

Site & development

Location context

Actual

Vantage HKG2 Fo Tan | Fo Tan | Hong Kong | HK

Source

Location context

Actual

Vantage HKG2 Fo Tan | Fo Tan | Hong Kong | HK

Source

Location context

Actual

Fo Tan, Hong Kong, HK

Source

Development detail

Actual

13-Story Tier III facility; 10 data modules; 185,000 square feet; 13 MW critical IT load.

Source

Additional project facts

Lifecycle status

Actual

Operational

Source

Capacity basis

Actual

Vantage Data Centers publishes 13 MW of critical IT capacity for this record boundary.

Source

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

13 MW facility or campus design capacity.

Source

Project boundary

Actual

Vantage HKG2 Fo Tan

Source

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

13 MW facility or campus design capacity.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Energized

China Light & Power feeds, N+1 block-redundant electrical systems, modular chillers and carrier-neutral connectivity.

Cooling system

Operational

Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (2)
Vantage HKG1 On Lok Data Center

Operating · Fanling, New Territories, Hong Kong, Hong Kong SAR China

Shared participant: CLP Power Hong Kong · Shared participant: Vantage Data Centers · Same market: Hong Kong, Hong Kong SAR China

Compare in a collection
Vantage HKG3 Kwai Chung Data Center

Operating · Kwai Chung, Hong Kong, Hong Kong SAR China

Shared participant: CLP Power Hong Kong · Shared participant: Vantage Data Centers · Same market: Hong Kong, Hong Kong SAR China

Compare in a collection