Scope and capacity

Vantage's Cardiff campus is a large UK hyperscale site with two facilities operating and a third planned. Full build is designed for 148 MW of critical IT capacity. Vantage Data Centers is publicly identified in the project record for Newport, Wales, GB. The disclosed development record includes 46-acre campus; three data centers at full build; two currently operational; 148 MW planned critical IT capacity. Power and infrastructure include high-density UK campus with renewable power, flexible cooling and multi-building redundancy. Vantage identifies 148 MW of critical IT capacity for CWL1 at full build.

Headline: 148 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Celtic Way | Coedkernew | Newport | Wales

Actual · Vantage CWL1 Cardiff Data Center Campus (Project)

Claim 59546 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage CWL1 campus profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3278 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/fr/data-center-locations/emea/cardiff-united-kingdom/

Lifecycle status · Partially operational

Actual · Vantage CWL1 Cardiff Data Center Campus (Project)

Claim 59547 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage CWL1 campus profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3278 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/fr/data-center-locations/emea/cardiff-united-kingdom/

Reported capacity · 148 MW

Design · Vantage CWL1 Cardiff Data Center Campus (Project)

Claim 59548 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Vantage CWL1 campus profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3278 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/fr/data-center-locations/emea/cardiff-united-kingdom/

Capacity basis · Vantage identifies 148 MW of critical IT capacity for CWL1 at full build.

Actual · Vantage CWL1 Cardiff Data Center Campus (Project)

Claim 59549 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage CWL1 campus profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3278 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/fr/data-center-locations/emea/cardiff-united-kingdom/

Development scale · 46-Acre campus

Actual · Vantage CWL1 Cardiff Data Center Campus (Project)

Claim 107804 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage CWL1 campus profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3278 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/fr/data-center-locations/emea/cardiff-united-kingdom/

  2. Vantage Cardiff current campus profile

    Vantage Data Centers · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6064 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/emea/cardiff-united-kingdom/

Development milestone · Three data centers at full build

Actual · Vantage CWL1 Cardiff Data Center Campus (Project)

Claim 107805 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage CWL1 campus profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3278 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/fr/data-center-locations/emea/cardiff-united-kingdom/

  2. Vantage Cardiff current campus profile

    Vantage Data Centers · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6064 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/emea/cardiff-united-kingdom/

Power arrangement · Two currently operational

Actual · Vantage CWL1 Cardiff Data Center Campus (Project)

Claim 107806 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage CWL1 campus profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3278 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/fr/data-center-locations/emea/cardiff-united-kingdom/

  2. Vantage Cardiff current campus profile

    Vantage Data Centers · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6064 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/emea/cardiff-united-kingdom/

Site configuration · 148 MW planned critical IT capacity.

Actual · Vantage CWL1 Cardiff Data Center Campus (Project)

Claim 107807 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage CWL1 campus profile

    Vantage Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3278 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/fr/data-center-locations/emea/cardiff-united-kingdom/

  2. Vantage Cardiff current campus profile

    Vantage Data Centers · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6064 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/emea/cardiff-united-kingdom/

Counterparties and capital

Vantage Data Centers · Developer · CMP-0109