Vantage BER1 Berlin Data Center Campus

PRJ-0765 · Site · Berlin area, Brandenburg, Germany

Record last updated Oct 28, 2026

Scope and capacity

Vantage's first Berlin campus is designed for 56 MW of critical IT capacity across a phased multi-building footprint. Vantage Data Centers is publicly identified in the project record for Berlin area, Berlin metro, Brandenburg, DE. The disclosed development record includes 56 MW planned critical IT capacity; Berlin-area campus; phased multi-building development. Power and infrastructure include berlin-region hyperscale campus with scalable electrical and mechanical systems. Vantage's BER1 campus profile identifies 56 MW of critical IT capacity.

Headline: 56 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · BER1 campus | Berlin metropolitan area | Germany

Actual · Vantage BER1 Berlin Data Center Campus (Project)

Claim 59582 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage BER1 campus overview

    Vantage Data Centers · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-3289 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/wp-content/uploads/2021/05/VDC_DataSheet_Berlin-I_BER1_FR.pdf

Lifecycle status · Partially operational

Actual · Vantage BER1 Berlin Data Center Campus (Project)

Claim 59583 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage BER1 campus overview

    Vantage Data Centers · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-3289 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/wp-content/uploads/2021/05/VDC_DataSheet_Berlin-I_BER1_FR.pdf

Reported capacity · 56 MW

Design · Vantage BER1 Berlin Data Center Campus (Project)

Claim 59584 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Vantage BER1 campus overview

    Vantage Data Centers · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-3289 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/wp-content/uploads/2021/05/VDC_DataSheet_Berlin-I_BER1_FR.pdf

Capacity basis · Vantage's BER1 campus profile identifies 56 MW of critical IT capacity.

Actual · Vantage BER1 Berlin Data Center Campus (Project)

Claim 59585 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage BER1 campus overview

    Vantage Data Centers · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-3289 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/wp-content/uploads/2021/05/VDC_DataSheet_Berlin-I_BER1_FR.pdf

Development scale · 56 MW planned critical IT capacity

Actual · Vantage BER1 Berlin Data Center Campus (Project)

Claim 107880 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Berlin I current campus profile

    Vantage Data Centers · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6083 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/emea/berlin-i-germany/

  2. Vantage BER1 campus overview

    Vantage Data Centers · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-3289 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/wp-content/uploads/2021/05/VDC_DataSheet_Berlin-I_BER1_FR.pdf

Development milestone · Berlin area campus

Actual · Vantage BER1 Berlin Data Center Campus (Project)

Claim 107881 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Berlin I current campus profile

    Vantage Data Centers · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6083 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/emea/berlin-i-germany/

  2. Vantage BER1 campus overview

    Vantage Data Centers · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-3289 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/wp-content/uploads/2021/05/VDC_DataSheet_Berlin-I_BER1_FR.pdf

Power arrangement · Phased multi building development.

Actual · Vantage BER1 Berlin Data Center Campus (Project)

Claim 107882 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Berlin I current campus profile

    Vantage Data Centers · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6083 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/emea/berlin-i-germany/

  2. Vantage BER1 campus overview

    Vantage Data Centers · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-3289 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/wp-content/uploads/2021/05/VDC_DataSheet_Berlin-I_BER1_FR.pdf

Boundary context · BER1 campus | Berlin metropolitan area | Germany

Actual · Vantage BER1 Berlin Data Center Campus (Project)

Claim 107883 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Vantage Berlin I current campus profile

    Vantage Data Centers · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6083 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/data-center-locations/emea/berlin-i-germany/

  2. Vantage BER1 campus overview

    Vantage Data Centers · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-3289 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://vantage-dc.com/wp-content/uploads/2021/05/VDC_DataSheet_Berlin-I_BER1_FR.pdf

Counterparties and capital

Vantage Data Centers · Developer · CMP-0109

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.