Cartis diligence evidence schedule
US Signal OR01 Bend Data Center
PRJ-1256 · Site · Bend, Oregon, United States
Record last updated Oct 28, 2026
Scope and capacity
US Signal OR01 Bend Data Center is an operating US Signal data-center facility in Bend, Oregon. US Signal's OR01 facility at 20845 Sockeye Place; malformed UPS units on the operator page are excluded. The retrofit records utility feed capacity: 2500 kVA; backup generation capacity: 2000 kW; cooling capacity: 256 tons. Utility service, UPS, standby generation, cooling, facility power and IT load are kept in their source-defined scopes rather than collapsed into one capacity number. Where reliable public evidence for ownership, project financing, permitting, tenants or water arrangements was not established, Cartis records the research gap explicitly instead of inferring a fact. The current operator page's UPS field is malformed and is withheld rather than converted into a false electrical value.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (6)
Facility identity · US Signal OR01 Bend Data Center
Actual · US Signal OR01 Bend Data Center (Project)
Claim 157797 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OR01 Bend data center
US Signal · Document date: Sep 4, 2026 · Primary
Source reference: SRC-7826 · Company announcement · Recorded authority: Party primary
Source URL
https://ussignal.com/data-centers/or01-bend/
https://ussignal.com/data-centers/or01-bend/
- US Signal’s OneNeck acquisition expands nationwide footprint
Lightwave Online · Document date: Jun 3, 2024 · Corroborating
Source reference: SRC-7827 · News report · Recorded authority: Secondary
Source URL
https://www.lightwaveonline.com/home/article/55055663/us-signals-oneneck-acquisition-expands-nationwide-data-center-footprint-it-network
https://www.lightwaveonline.com/home/article/55055663/us-signals-oneneck-acquisition-expands-nationwide-data-center-footprint-it-network
Utility feed capacity · 2,500 kVA
Actual · US Signal OR01 Bend Data Center (Project)
Claim 157868 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OR01 Bend data center
US Signal · Document date: Sep 4, 2026 · Primary
Source reference: SRC-7826 · Company announcement · Recorded authority: Party primary
Source URL
https://ussignal.com/data-centers/or01-bend/
https://ussignal.com/data-centers/or01-bend/
Backup generation capacity · 2,000 kW
Actual · US Signal OR01 Bend Data Center (Project)
Claim 157869 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Generation capacity; not IT capacity
- OR01 Bend data center
US Signal · Document date: Sep 4, 2026 · Primary
Source reference: SRC-7826 · Company announcement · Recorded authority: Party primary
Source URL
https://ussignal.com/data-centers/or01-bend/
https://ussignal.com/data-centers/or01-bend/
Cooling capacity · 256 tons
Actual · US Signal OR01 Bend Data Center (Project)
Claim 157871 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OR01 Bend data center
US Signal · Document date: Sep 4, 2026 · Primary
Source reference: SRC-7826 · Company announcement · Recorded authority: Party primary
Source URL
https://ussignal.com/data-centers/or01-bend/
https://ussignal.com/data-centers/or01-bend/
Carrier count · 6 carriers
Actual · US Signal OR01 Bend Data Center (Project)
Claim 157872 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OR01 Bend data center
US Signal · Document date: Sep 4, 2026 · Primary
Source reference: SRC-7826 · Company announcement · Recorded authority: Party primary
Source URL
https://ussignal.com/data-centers/or01-bend/
https://ussignal.com/data-centers/or01-bend/
Facility tier designation · Tier 3
Actual · US Signal OR01 Bend Data Center (Project)
Claim 157873 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- OR01 Bend data center
US Signal · Document date: Sep 4, 2026 · Primary
Source reference: SRC-7826 · Company announcement · Recorded authority: Party primary
Source URL
https://ussignal.com/data-centers/or01-bend/
https://ussignal.com/data-centers/or01-bend/
Counterparties and capital
US Signal · Operator · CMP-1691
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.