Data center siteSite record

TeraWulf Muskie Data Campus

Grayson, Kentucky, United StatesPreconstruction
Capacity
800 MW
Planned critical IT
Lead participant
TeraWulf
Developer
Last updated
Aug 27, 2026
Most recent public record update

About TeraWulf Muskie Data Campus

TeraWulf acquired Muskie Data as a large AI and HPC development campus in Eastern Kentucky. Its current platform presentation identifies approximately 800 MW of planned critical IT capacity, while the electric-service framework supports up to 1 GW gross. TeraWulf, Kentucky Power is associated with the development in Grayson, Grayson area, KY, US. The disclosed development scope includes approximately 800 MW planned critical IT; up to 1 GW utility service; phased delivery targeted from 2028. Power and physical infrastructure include planned 345 kV substation tied to the regional 765 kV transmission network. TeraWulf identifies about 800 MW of planned critical IT capacity at Muskie.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load800 MWDesign · TeraWulf Muskie Data Campus
It Load800 MWDesign · TeraWulf Muskie Data Campus

Development

1 phases · 2 milestones
Development programAnnounced Or Preconstruction

Project-wide phase for TeraWulf Muskie Data Campus; capacity class is it load.

Aug 5, 2026
Muskie Data Eastern Kentucky development disclosed
Completed
Planning and permitting with contracted utility service
Forecast

Infrastructure

Electric GridPlanned Or Represented

800 MW

TeraWulf identifies about 800 MW of planned critical IT capacity at Muskie.

Site FacilityPlanned Or Represented

Planned 345 kV substation tied to the regional 765 kV transmission network.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
Muskie Data Campus | Grayson | Eastern Kentucky
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
800 MW
Design
Capacity Basis
TeraWulf identifies about 800 MW of planned critical IT capacity at Muskie.
Actual
Location Context
Muskie Data Campus | Grayson | Eastern Kentucky
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
800 MW
Design
Capacity Basis
TeraWulf identifies about 800 MW of planned critical IT capacity at Muskie.
Actual
Development Scale
Approximately 800 MW planned critical IT
Actual
Development Milestone
Up to 1 GW utility service
Actual
Power Arrangement
Phased delivery targeted from 2028.
Actual
Site Configuration
Muskie Data Campus | Grayson | Eastern Kentucky
Actual