Cartis diligence evidence schedule
TeraWulf Justified Data Hawesville Campus
PRJ-0622 · Site · Hawesville, Kentucky, United States
Record last updated Oct 28, 2026
Scope and capacity
On August 24, 2026, TeraWulf announced Kentucky Public Service Commission approval of the 482 MW retail electric-service agreement for Justified. The announcement date is not assumed to be the order date, and the electrical-service amount is distinct from contracted critical IT capacity or commissioned load. TeraWulf is developing the Justified Data campus in Hawesville, Kentucky for Anthropic. The company reports 401 MW of leased critical IT capacity and targets phased delivery from the second half of 2027 through the first half of 2028. Energized substation, high-voltage lines, and regional transmission access are identified by TeraWulf.
Headline: 401 MW Contracted
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Location context · Justified Data campus | Hawesville | Kentucky | United States
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 55492 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
Lifecycle status · Construction
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 55493 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
Reported capacity · 401 MW
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 55494 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
Capacity basis · Source stated leased critical IT capacity
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 55495 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
Project identity · TeraWulf Justified Data Hawesville Campus
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 114519 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
- Big Rivers Electric large-load contract filing
Kentucky Public Service Commission · Document date: Apr 14, 2026 · Corroborating
Source reference: SRC-6369 · Government record · Recorded authority: Official primary
Source URL
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
Lifecycle status · Under construction
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 114520 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
- Big Rivers Electric large-load contract filing
Kentucky Public Service Commission · Document date: Apr 14, 2026 · Corroborating
Source reference: SRC-6369 · Government record · Recorded authority: Official primary
Source URL
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
Location · Hawesville, KY, US
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 114521 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
- Big Rivers Electric large-load contract filing
Kentucky Public Service Commission · Document date: Apr 14, 2026 · Corroborating
Source reference: SRC-6369 · Government record · Recorded authority: Official primary
Source URL
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
Participant roles · TeraWulf, Anthropic
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 114522 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
- Big Rivers Electric large-load contract filing
Kentucky Public Service Commission · Document date: Apr 14, 2026 · Corroborating
Source reference: SRC-6369 · Government record · Recorded authority: Official primary
Source URL
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
Capacity · 401 MW
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 114523 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
- Big Rivers Electric large-load contract filing
Kentucky Public Service Commission · Document date: Apr 14, 2026 · Corroborating
Source reference: SRC-6369 · Government record · Recorded authority: Official primary
Source URL
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
Capacity basis · 401 MW contracted critical IT capacity
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 114524 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
- Big Rivers Electric large-load contract filing
Kentucky Public Service Commission · Document date: Apr 14, 2026 · Corroborating
Source reference: SRC-6369 · Government record · Recorded authority: Official primary
Source URL
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
Development scale · 401 MW leased critical IT; Anthropic tenant
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 114525 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
- Big Rivers Electric large-load contract filing
Kentucky Public Service Commission · Document date: Apr 14, 2026 · Corroborating
Source reference: SRC-6369 · Government record · Recorded authority: Official primary
Source URL
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
Infrastructure · Energized substation, high voltage lines, and regional transmission access are identified by TeraWulf.
Actual · TeraWulf Justified Data Hawesville Campus (Project)
Claim 114526 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- TeraWulf Q2 2026 Business Update
TeraWulf · Document date: Aug 5, 2026 · Primary
Source reference: SRC-2993 · Regulatory record · Recorded authority: Party primary
Source URL
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000162/terawulfq22026investorpr.htm
- Big Rivers Electric large-load contract filing
Kentucky Public Service Commission · Document date: Apr 14, 2026 · Corroborating
Source reference: SRC-6369 · Government record · Recorded authority: Official primary
Source URL
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
https://psc.ky.gov/pscscf/2026%20cases/2026-00115/20260414_Big%20Rivers%20Electric%20Corporation%20Contract%20Filing.pdf
Counterparties and capital
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.