Scope and capacity

TAC Data Centers, a subsidiary of The Ardent Companies, proposes a gigawatt-scale campus on about 1,000 acres in eastern Wythe County, Virginia. The plan calls for nine to eleven buildings totaling roughly 3.5–4 million square feet, with initial delivery targeted around 2029 and power infrastructure still a gating item.

Headline: 1,000 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · TAC Data Centers - Wythe County | Fort Chiswell | Virginia | US

Actual · TAC Data Centers - Wythe County (Project)

Claim 71866 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TAC Data Centers - Wythe County public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4119 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/virginia/

Lifecycle status · Proposed

Actual · TAC Data Centers - Wythe County (Project)

Claim 71867 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TAC Data Centers - Wythe County public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4119 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/virginia/

Reported capacity · 1,000 MW

Planned / design or future potential · TAC Data Centers - Wythe County (Project)

Claim 71868 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. TAC Data Centers - Wythe County public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4119 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/virginia/

Capacity basis · 1,000 MW future full build site capacity; not measured operating IT load.

Actual · TAC Data Centers - Wythe County (Project)

Claim 71869 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. TAC Data Centers - Wythe County public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4119 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/virginia/

Site area · 1,000 acres

Reported rounded · TAC Data Centers - Wythe County (Project)

Claim 77743 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Gigawatt data center planned for Wythe County

    Cardinal News · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-4418 · News report · Recorded authority: Secondary

    Source URL

    https://cardinalnews.org/2026/06/04/gigawatt-data-center-project-planned-for-wythe-county/

Building count range · 9–11 Buildings

Reported rounded · TAC Data Centers - Wythe County (Project)

Claim 77744 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Gigawatt data center planned for Wythe County

    Cardinal News · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-4418 · News report · Recorded authority: Secondary

    Source URL

    https://cardinalnews.org/2026/06/04/gigawatt-data-center-project-planned-for-wythe-county/

Gross floor area range · 3.5–4.0 Million square feet

Reported rounded · TAC Data Centers - Wythe County (Project)

Claim 77745 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Gigawatt data center planned for Wythe County

    Cardinal News · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-4418 · News report · Recorded authority: Secondary

    Source URL

    https://cardinalnews.org/2026/06/04/gigawatt-data-center-project-planned-for-wythe-county/

First delivery target · 2029

Reported rounded · TAC Data Centers - Wythe County (Project)

Claim 77746 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Gigawatt data center planned for Wythe County

    Cardinal News · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-4418 · News report · Recorded authority: Secondary

    Source URL

    https://cardinalnews.org/2026/06/04/gigawatt-data-center-project-planned-for-wythe-county/

Counterparties and capital

TAC Data Centers · Developer · CMP-1526