Cartis diligence evidence schedule

Switch Atlanta Keep Campus

PRJ-0970 · Site · Atlanta, Georgia, United States

Record last updated Oct 28, 2026

Scope and capacity

Switch’s Keep Campus is an operating Atlanta-area campus with a 150 MW upon-completion boundary. A separate 2,000-plus-acre multi-gigawatt expansion concept is retained as future context and is not merged into the existing campus capacity. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Headline: 150 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (17)

Location context · Switch The Keep | Atlanta | GA | US

Actual · Switch Atlanta Keep Campus (Project)

Claim 66477 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Lifecycle status · Partially operational

Actual · Switch Atlanta Keep Campus (Project)

Claim 66478 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Reported capacity · 150 MW

Design · Switch Atlanta Keep Campus (Project)

Claim 66479 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Capacity basis · Switch publishes 150 MW of IT power for this project boundary.

Actual · Switch Atlanta Keep Campus (Project)

Claim 66480 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Location context · Switch The Keep | Atlanta | GA | US

Actual · Switch Atlanta Keep Campus (Project)

Claim 84412 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Lifecycle status · Partially operational

Actual · Switch Atlanta Keep Campus (Project)

Claim 84413 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Reported capacity · 150 MW

Design · Switch Atlanta Keep Campus (Project)

Claim 84414 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Capacity basis · 150 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · Switch Atlanta Keep Campus (Project)

Claim 84415 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Operator confirmed · Switch

Actual · Switch Atlanta Keep Campus (Project)

Claim 84416 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Project location · Atlanta, GA, US

Actual · Switch Atlanta Keep Campus (Project)

Claim 84417 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Current lifecycle · Partly operating with phased delivery or expansion underway

Actual · Switch Atlanta Keep Campus (Project)

Claim 84418 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Capacity classification · It load

Actual · Switch Atlanta Keep Campus (Project)

Claim 84419 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Capacity basis · 150 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Actual · Switch Atlanta Keep Campus (Project)

Claim 84420 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Customer utilization · Not publicly disclosed

Actual · Switch Atlanta Keep Campus (Project)

Claim 84421 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Identity boundary · This facility or named campus is tracked separately from adjacent buildings and broader operator portfolios

Actual · Switch Atlanta Keep Campus (Project)

Claim 84422 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. High-Technology Data Center Equipment Exemption

    Georgia Department of Revenue · Document date: Aug 29, 2026 · Primary

    Source reference: SRC-4735 · Government record · Recorded authority: Official primary

    Source URL

    https://dor.georgia.gov/high-technology-data-center-equipment-exemption

Source refresh date · 2026-08-29

Actual · Switch Atlanta Keep Campus (Project)

Claim 84423 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Separate expansion site area · 2,000 acres

Forecast · Switch Atlanta Keep Campus (Project)

Claim 84425 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

  1. Switch Atlanta Keep Campus official profile

    Switch · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3760 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.switch.com/atlanta/

Counterparties and capital

Switch · Developer · CMP-0645

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.