Data center siteSite record

STT Johor Campus / STT Johor 1

Nusa Cemerlang Industrial Park, Iskandar Puteri, Johor, JHR, MalaysiaUnder construction
Capacity
No public figure
Lead participant
ST Telemedia Global Data Centres
Operator
Last updated
Aug 22, 2026
Most recent public record update

About STT Johor Campus / STT Johor 1

STT Johor 1 is the first 16 MW facility under construction within a campus with 120 MW of future IT development potential. Current operator material expects completion by 2027.

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential120 MWProposal · STT Johor full campus
It Load16 MWDesign · STT Johor 1

Development

2 phases · 3 milestones
STT Johor full campusAnnounced Or Preconstruction

Future campus envelope; later building count and phasing undisclosed.

STT Johor 1Under Construction

First facility only, designed for 16 MW IT.

1 building

Feb 24, 2025
STT Johor 1 groundbreaking
Completed
Dec 31, 2026
Original STT Johor 1 operation target
Cancelled
Dec 31, 2027
Current STT Johor 1 completion wording
Forecast

Infrastructure

Electric GridPlanned Or Represented

nearby substations; development design.

FiberPlanned Or Represented

data center interconnect; planned.

Renewable Energy SupplyPotential Or Planned

renewable electricity supply; supplier discussions.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 2Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

10 facts
Project Status
Under Development; STT Johor 1 under construction
Actual
Campus It Development Potential
120 MW
Proposal
Site Area
>22 acres
Actual
Designed It Load
16 MW
Design
Groundbreaking Date
2025-02-24
Actual
Completion Target
2,027
Forecast
Distance To Singapore
15 km
Actual
Regional Interconnection
Ready to connect to STT Singapore 5 and STT GDC regional DCI hubs
Design
Energy Supply Goal
Renewable and low carbon energy sources
Forecast
Workforce Mou
MOU with Johor Talent Development Council
Actual