All records
Data center siteSite record
Stargate The Barn — Saline Township
Saline Township, Michigan, United StatesUnder construction
Capacity
1,000 MW
Planned critical IT
Lead participant
Oracle
Developer
Last updated
Aug 27, 2026
Most recent public record update
About Stargate The Barn — Saline Township
OpenAI and its partners broke ground in June 2026 on The Barn, a planned 1 GW Stargate data center campus in Saline Township, Michigan. Oracle, Related Digital and Walbridge are named project partners, and the design includes closed-loop cooling. Separate utility-service contracts should not be read as operating IT capacity.
Capacity
Planned critical ITOperating capacity—An operating IT-capacity figure has not been publicly disclosed.
Design1,000 MWDesign · Stargate The Barn — Saline Township
It Load1,000 MWDesign · Stargate The Barn — Saline Township
It Load1,000 MW planned campus IT capacityActual · Stargate The Barn — Saline Township
Development
1 phases · 2 milestonesConstruction programUnder Construction
Stargate The Barn — Saline Township: Construction program.
Jun 1, 2026
Stargate The Barn — Saline Township — Construction program
In Progress—
OpenAI and its partners broke ground in June 2026 on The Barn, a planned 1 GW Stargate data center campus in Saline Township, Michigan.
In ProgressInfrastructure
Electric GridPlanned Or Represented
1,000 MW
1,000 MW planned campus IT capacity
Site FacilityPlanned Or Represented
Separate utility-service contracts should not be read as operating IT capacity.
Project map
0 of 1 project point mappedInfrastructure facts
2
Mapped records
1
Capacity figures
1
No map point available
Power & interconnection: 1Site systems: 1
Facts & sources
Published claims and their source links.
Location ContextThe Barn | Saline Township | Michigan | United StatesActual
The Barn | Saline Township | Michigan | United States
Lifecycle StatusConstructionActual
Construction
Reported Capacity1,000 MWDesign
1,000 MW
Capacity BasisSource stated campus capacityActual
Source stated campus capacity
Project IdentityStargate The Barn — Saline TownshipActual
Stargate The Barn — Saline Township
Lifecycle StatusConstruction programActual
Construction program
LocationSaline Township, Washtenaw County, MI, USActual
Saline Township, Washtenaw County, MI, US
Participant RolesOpenAI, Oracle, Related Digital, WalbridgeActual
OpenAI, Oracle, Related Digital, Walbridge
Capacity1,000 MWDesign
1,000 MW
Capacity Basis1,000 MW planned campus IT capacityActual
1,000 MW planned campus IT capacity
Development ScaleOpenAI and its partners broke ground in June 2026 on The Barn, a planned 1 GW Stargate data center campus in Saline Township, Michigan. Oracle, Related Digital and Walbridge are named project partners, and the design includes closed loop coolingActual
OpenAI and its partners broke ground in June 2026 on The Barn, a planned 1 GW Stargate data center campus in Saline Township, Michigan. Oracle, Related Digital and Walbridge are named project partners, and the design includes closed loop cooling
InfrastructureSeparate utility service contracts should not be read as operating IT capacity.Actual
Separate utility service contracts should not be read as operating IT capacity.