Skip to content
All records
Data center siteSite record

Stargate The Barn — Saline Township

Saline Township, Michigan, United StatesUnder construction
Capacity
1,000 MW
Planned critical IT
Lead participant
Oracle
Developer
Last updated
Aug 27, 2026
Most recent public record update

About Stargate The Barn — Saline Township

OpenAI and its partners broke ground in June 2026 on The Barn, a planned 1 GW Stargate data center campus in Saline Township, Michigan. Oracle, Related Digital and Walbridge are named project partners, and the design includes closed-loop cooling. Separate utility-service contracts should not be read as operating IT capacity.

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design1,000 MWDesign · Stargate The Barn — Saline Township
It Load1,000 MWDesign · Stargate The Barn — Saline Township
It Load1,000 MW planned campus IT capacityActual · Stargate The Barn — Saline Township

Development

1 phases · 2 milestones
Construction programUnder Construction

Stargate The Barn — Saline Township: Construction program.

Jun 1, 2026
Stargate The Barn — Saline Township — Construction program
In Progress
OpenAI and its partners broke ground in June 2026 on The Barn, a planned 1 GW Stargate data center campus in Saline Township, Michigan.
In Progress

Infrastructure

Electric GridPlanned Or Represented

1,000 MW

1,000 MW planned campus IT capacity

Site FacilityPlanned Or Represented

Separate utility-service contracts should not be read as operating IT capacity.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
The Barn | Saline Township | Michigan | United States
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
1,000 MW
Design
Capacity Basis
Source stated campus capacity
Actual
Project Identity
Stargate The Barn — Saline Township
Actual
Lifecycle Status
Construction program
Actual
Location
Saline Township, Washtenaw County, MI, US
Actual
Participant Roles
OpenAI, Oracle, Related Digital, Walbridge
Actual
Capacity
1,000 MW
Design
Capacity Basis
1,000 MW planned campus IT capacity
Actual
Development Scale
OpenAI and its partners broke ground in June 2026 on The Barn, a planned 1 GW Stargate data center campus in Saline Township, Michigan. Oracle, Related Digital and Walbridge are named project partners, and the design includes closed loop cooling
Actual
Infrastructure
Separate utility service contracts should not be read as operating IT capacity.
Actual