Stargate Lordstown

Lordstown, Ohio, United StatesProposed
Evidence
Planned / design
750 MW
Updated
Oct 28, 2026

SoftBank has broken ground on a Stargate data center at the former Lordstown, Ohio industrial site. OpenAI says the campus is part of a two-site SoftBank partnership capable of scaling to 1.5 GW across the pair, with Lordstown targeted for operation in 2026; 750 MW is therefore a shared-program allocation, not confirmed operating load.

Capacity

Reported capacity

Planned / design or future potential

750 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Construction after groundbreakingAnnounced or preconstruction

SoftBank has broken ground on a Stargate data center at the former Lordstown, Ohio industrial site. OpenAI says the campus is part of a two-site SoftBank partnership capable of scaling to 1.5 GW across the pair, with Lordstown targeted for operation in 2026; 750 MW is therefore a shared-program allocation, not confirmed operating load.

Milestones (2)
Lordstown announced as a Stargate site after groundbreaking

Sep 23, 2025 · Recorded actual event

Completed · Announced

Source not linked
Target operational year

2026 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Stargate

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

Stargate Lordstown | Lordstown | Ohio | US

Source

Construction status

Actual

Groundbreaking completed

Source

Additional project facts

Lifecycle status

Actual

Proposed

Source

Capacity basis

Actual

750 MW future full build site capacity; not measured operating IT load.

Source

Program scope

Actual

Shared across two SoftBank/OpenAI sites

Source

Target operations

Reported rounded

2026

Source

Infrastructure & permits

Technical details (1)
Electric grid

Under construction

750 MW

Allocated half of a 1.5 GW two-site program; not verified operating load.

Public-source research. Plans may change. See Evidence for sources and qualifications.