Scope and capacity

STACK's NVAL1 campus in Manassas is planned for at least seven data centers and 250 MW of scalable critical capacity. STACK Infrastructure is publicly identified in the project record for Manassas, Prince William County, VA, US. The disclosed development record includes 125-acre campus; at least seven data centers; 250 MW planned critical capacity; dedicated onsite substation. Power and infrastructure include large hyperscale campus with extensive fiber access and a dedicated onsite substation. STACK's NVAL1 campus plan provides 250 MW of scalable critical capacity.

Headline: 250 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · NVAL1 campus | Manassas | Prince William County | Virginia

Actual · STACK NVAL1 Manassas Data Center Campus (Project)

Claim 59526 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK NVAL1 campus overview

    STACK Infrastructure · Document date: Dec 7, 2022 · Primary

    Source reference: SRC-3272 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/wp-content/uploads/2020/11/NVAL1_Campus_120722.pdf

Lifecycle status · Construction

Actual · STACK NVAL1 Manassas Data Center Campus (Project)

Claim 59527 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK NVAL1 campus overview

    STACK Infrastructure · Document date: Dec 7, 2022 · Primary

    Source reference: SRC-3272 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/wp-content/uploads/2020/11/NVAL1_Campus_120722.pdf

Reported capacity · 250 MW

Planned / design or future potential · STACK NVAL1 Manassas Data Center Campus (Project)

Claim 59528 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. STACK NVAL1 campus overview

    STACK Infrastructure · Document date: Dec 7, 2022 · Primary

    Source reference: SRC-3272 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/wp-content/uploads/2020/11/NVAL1_Campus_120722.pdf

Capacity basis · STACK's NVAL1 campus plan provides 250 MW of scalable critical capacity.

Actual · STACK NVAL1 Manassas Data Center Campus (Project)

Claim 59529 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK NVAL1 campus overview

    STACK Infrastructure · Document date: Dec 7, 2022 · Primary

    Source reference: SRC-3272 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/wp-content/uploads/2020/11/NVAL1_Campus_120722.pdf

Development scale · 125-Acre campus

Actual · STACK NVAL1 Manassas Data Center Campus (Project)

Claim 107764 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK NVAL1 campus overview

    STACK Infrastructure · Document date: Dec 7, 2022 · Primary

    Source reference: SRC-3272 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/wp-content/uploads/2020/11/NVAL1_Campus_120722.pdf

  2. STACK and Peterson announce Manassas campus

    STACK Infrastructure · Document date: Jan 22, 2020 · Corroborating

    Source reference: SRC-6055 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/about/news-press/press-releases/stack-infrastructure-and-peterson-companies-announce-development-of-125-acre-hyperscale-data-center-campus-in-prince-william-county-va/

Development milestone · At least seven data centers

Actual · STACK NVAL1 Manassas Data Center Campus (Project)

Claim 107765 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK NVAL1 campus overview

    STACK Infrastructure · Document date: Dec 7, 2022 · Primary

    Source reference: SRC-3272 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/wp-content/uploads/2020/11/NVAL1_Campus_120722.pdf

  2. STACK and Peterson announce Manassas campus

    STACK Infrastructure · Document date: Jan 22, 2020 · Corroborating

    Source reference: SRC-6055 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/about/news-press/press-releases/stack-infrastructure-and-peterson-companies-announce-development-of-125-acre-hyperscale-data-center-campus-in-prince-william-county-va/

Power arrangement · 250 MW planned critical capacity

Actual · STACK NVAL1 Manassas Data Center Campus (Project)

Claim 107766 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK NVAL1 campus overview

    STACK Infrastructure · Document date: Dec 7, 2022 · Primary

    Source reference: SRC-3272 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/wp-content/uploads/2020/11/NVAL1_Campus_120722.pdf

  2. STACK and Peterson announce Manassas campus

    STACK Infrastructure · Document date: Jan 22, 2020 · Corroborating

    Source reference: SRC-6055 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/about/news-press/press-releases/stack-infrastructure-and-peterson-companies-announce-development-of-125-acre-hyperscale-data-center-campus-in-prince-william-county-va/

Site configuration · Dedicated onsite substation.

Actual · STACK NVAL1 Manassas Data Center Campus (Project)

Claim 107767 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. STACK NVAL1 campus overview

    STACK Infrastructure · Document date: Dec 7, 2022 · Primary

    Source reference: SRC-3272 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/wp-content/uploads/2020/11/NVAL1_Campus_120722.pdf

  2. STACK and Peterson announce Manassas campus

    STACK Infrastructure · Document date: Jan 22, 2020 · Corroborating

    Source reference: SRC-6055 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.stackinfra.com/about/news-press/press-releases/stack-infrastructure-and-peterson-companies-announce-development-of-125-acre-hyperscale-data-center-campus-in-prince-william-county-va/

Counterparties and capital

STACK Infrastructure · Developer · CMP-0102

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.