STACK ICN01 Incheon Data Center
- Planned critical IT
- 48 MW
- Updated
- Oct 28, 2026
- Utility
- KEPCO
STACK ICN01 Incheon Data Center, also known as STACK ICN01, is a data center project in Incheon, Incheon, KR developed and operated by STACK Infrastructure. Single-building 48 MW facility in Incheon, a western suburb of Seoul, developed with ESR. Secured KEPCO power, robust network connectivity and high-density-capable floor and cooling specifications. 48 MW is the planned IT-load boundary for the phased Bupyeong/ICN01 facility; the partner’s 80 MW figure is a wider utility envelope and is not substituted for IT capacity.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
48 MW is the planned IT-load boundary for the phased Bupyeong/ICN01 facility; the partner’s 80 MW figure is a wider utility envelope and is not substituted for IT capacity.
Milestones (2)
Sep 8, 2022 · Recorded actual event
Completed · Announced
Source not linked2025 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- ESR Data Centres current project portfolio · Aug 29, 2026 · Primary
Developer
Sources by role
Developer (1)
- STACK and ESR announce 48MW Seoul-area data center · Sep 8, 2022 · Primary
Other participants (1)
Utility provider
Sources by role
Utility provider (1)
- ESR Data Centres current project portfolio · Aug 29, 2026 · Primary
Site & development
Additional project facts
Capacity basis
ActualSTACK Infrastructure publishes 48 MW of critical IT capacity for this record boundary.
SourceCapacity basis
Actual48 MW is the planned IT-load boundary for the phased Bupyeong/ICN01 facility; the partner’s 80 MW figure is a wider utility envelope and is not substituted for IT capacity.
SourceInfrastructure & permits
Technical details (3)
Energized
Secured KEPCO power, robust network connectivity and high-density-capable floor and cooling specifications.
Energized
STACK markets diverse fiber and carrier-neutral deployment options; installed and contracted capacity remain distinct.
Secured or contracted
80 MW gross
KEPCO/partner utility envelope; 48 MW is the separate IT-load design.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.