Cartis diligence evidence schedule
SoftBank Tomakomai AI Data Center
PRJ-0643 · Site · Tomakomai, Hokkaido, Japan
Record last updated Oct 28, 2026
Scope and capacity
SoftBank is constructing an AI data center in Tomakomai, Hokkaido. The company targets an initial 50 MW-scale facility in fiscal 2026 and states that the site is intended to expand beyond 300 MW of future receiving capacity. AI-focused facility designed to use Hokkaido renewable power and support advanced cooling.
Headline: 300 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Location context · SoftBank AI data center | Tomakomai | Hokkaido | Japan
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 55576 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Lifecycle status · Construction
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 55577 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Reported capacity · 300 MW
Design · SoftBank Tomakomai AI Data Center (Project)
Claim 55578 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Capacity basis · Source states future receiving capacity will exceed 300 MW; stored floor value
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 55579 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Project identity · SoftBank Tomakomai AI Data Center
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 114687 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Next-generation infrastructure program
SoftBank · Document date: Jan 1, 2026 · Corroborating
Source reference: SRC-6395 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Lifecycle status · Under construction
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 114688 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Next-generation infrastructure program
SoftBank · Document date: Jan 1, 2026 · Corroborating
Source reference: SRC-6395 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Location · Tomakomai, Hokkaido, JP
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 114689 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Next-generation infrastructure program
SoftBank · Document date: Jan 1, 2026 · Corroborating
Source reference: SRC-6395 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Participant roles · SoftBank
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 114690 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Next-generation infrastructure program
SoftBank · Document date: Jan 1, 2026 · Corroborating
Source reference: SRC-6395 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Capacity · 300 MW
Planned / design or future potential · SoftBank Tomakomai AI Data Center (Project)
Claim 114691 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Next-generation infrastructure program
SoftBank · Document date: Jan 1, 2026 · Corroborating
Source reference: SRC-6395 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Capacity basis · 300 MW planned or design IT capacity
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 114692 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Next-generation infrastructure program
SoftBank · Document date: Jan 1, 2026 · Corroborating
Source reference: SRC-6395 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Development scale · Construction underway; initial 50 MW scale in fiscal 2026
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 114693 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Next-generation infrastructure program
SoftBank · Document date: Jan 1, 2026 · Corroborating
Source reference: SRC-6395 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Infrastructure · AI-focused facility designed to use Hokkaido renewable power and support advanced cooling.
Actual · SoftBank Tomakomai AI Data Center (Project)
Claim 114694 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Next-generation infrastructure program
SoftBank · Document date: Jan 1, 2026 · Corroborating
Source reference: SRC-6395 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
https://www.softbank.jp/en/corp/sustainability/materiality/next-gen-infra/
- Toward the Completion of a Large-scale AI Data Center in Tomakomai
SoftBank · Document date: May 1, 2025 · Primary
Source reference: SRC-3016 · Company announcement · Recorded authority: Party primary
Source URL
https://www.softbank.jp/en/sbnews/entry/20250501_01
https://www.softbank.jp/en/sbnews/entry/20250501_01
Counterparties and capital
SoftBank Corp. · Developer · CMP-0706
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.