Cartis diligence evidence schedule
SoftBank France AI Data Center Program
PRJ-0370 · Program · France
Record last updated Oct 28, 2026
Scope and capacity
SoftBank France AI Data Center Program is a multi-site SoftBank/SB Energy France AI-infrastructure program covering Bosquel, Dunkirk and Bouchain; campus-specific claims stay on child records. SoftBank France AI Data Center Program is located in France, FR and is a program in preconstruction status.
Headline: See constituent sites
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Planned program capacity · 5 GW
Planned / design or future potential · SoftBank France AI Data Center Program (Project)
Claim 33821 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- SoftBank Group announces up to 5GW AI data center development program in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1896 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
- SoftBank plans up to 5GW data center buildout in France
Data Center Dynamics · Document date: May 30, 2026 · Corroborating
Source reference: SRC-1898 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/softbank-plans-up-to-5gw-data-center-buildout-in-france-investment-of-up-to-75bn/
https://www.datacenterdynamics.com/en/news/softbank-plans-up-to-5gw-data-center-buildout-in-france-investment-of-up-to-75bn/
Planned program investment up to · €75 billion
Actual · SoftBank France AI Data Center Program (Project)
Claim 33822 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SoftBank to spend EUR 75bn building AI data centres in France
Telecoms.com · Document date: Jun 1, 2026 · Corroborating
Source reference: SRC-1899 · News report · Recorded authority: Secondary
Source URL
https://www.telecoms.com/ai/softbank-to-spend-75bn-building-ai-data-centres-in-france
https://www.telecoms.com/ai/softbank-to-spend-75bn-building-ai-data-centres-in-france
- SoftBank Group announces up to 5GW AI data center development program in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1896 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
First phase capacity · 3.1 GW
Planned / design or future potential · SoftBank France AI Data Center Program (Project)
Claim 33823 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- SoftBank Group announces up to 5GW AI data center development program in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1896 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
First phase investment · €45 billion
Actual · SoftBank France AI Data Center Program (Project)
Claim 33824 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SoftBank Group announces up to 5GW AI data center development program in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1896 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
First phase target year · 2031
Actual · SoftBank France AI Data Center Program (Project)
Claim 33825 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SoftBank Group announces up to 5GW AI data center development program in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1896 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
Named first phase sites · 3 sites
Actual · SoftBank France AI Data Center Program (Project)
Claim 33826 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SoftBank Group announces up to 5GW AI data center development program in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1896 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
Planned program capacity · 5 GW
Planned / design or future potential · SoftBank France AI Data Center Program (Project)
Claim 34645 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- SoftBank Group to build 5 GW of AI data center capacity in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1934 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
- SoftBank plans up to 5 GW data-center buildout in France
Data Center Dynamics · Document date: May 30, 2026 · Corroborating
Source reference: SRC-7131 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/softbank-plans-up-to-5gw-data-center-buildout-in-france-investment-of-up-to-75bn/
https://www.datacenterdynamics.com/en/news/softbank-plans-up-to-5gw-data-center-buildout-in-france-investment-of-up-to-75bn/
Planned program investment up to · €75 billion
Actual · SoftBank France AI Data Center Program (Project)
Claim 34646 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SoftBank Group to build 5 GW of AI data center capacity in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1934 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
- SoftBank plans up to 5 GW data-center buildout in France
Data Center Dynamics · Document date: May 30, 2026 · Corroborating
Source reference: SRC-7131 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/softbank-plans-up-to-5gw-data-center-buildout-in-france-investment-of-up-to-75bn/
https://www.datacenterdynamics.com/en/news/softbank-plans-up-to-5gw-data-center-buildout-in-france-investment-of-up-to-75bn/
First phase capacity · 3.1 GW
Planned / design or future potential · SoftBank France AI Data Center Program (Project)
Claim 34647 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- SoftBank Group to build 5 GW of AI data center capacity in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1934 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
- SoftBank plans up to 5 GW data-center buildout in France
Data Center Dynamics · Document date: May 30, 2026 · Corroborating
Source reference: SRC-7131 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/softbank-plans-up-to-5gw-data-center-buildout-in-france-investment-of-up-to-75bn/
https://www.datacenterdynamics.com/en/news/softbank-plans-up-to-5gw-data-center-buildout-in-france-investment-of-up-to-75bn/
First phase investment · €45 billion
Actual · SoftBank France AI Data Center Program (Project)
Claim 34648 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SoftBank Group to build 5 GW of AI data center capacity in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1934 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
First phase target year · 2031
Actual · SoftBank France AI Data Center Program (Project)
Claim 34649 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SoftBank Group to build 5 GW of AI data center capacity in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1934 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
First phase site count · 3 sites
Actual · SoftBank France AI Data Center Program (Project)
Claim 34650 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- SoftBank Group to build 5 GW of AI data center capacity in France
SoftBank Group · Document date: May 31, 2026 · Primary
Source reference: SRC-1934 · Company announcement · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/press/20260531_0
https://group.softbank/en/news/press/20260531_0
Counterparties and capital
SB Energy · Developer · CMP-0908
€75,000,000,000 · May 31, 2026
Program envelope up to EUR 75 billion; first phase EUR 45 billion across three sites.
SoftBank Group Corp. (Program sponsor)
Sources (1)
Financing record 100; claim-specific source links appear in the exhibit sources where published.
€45,000,000,000 · May 31, 2026
First-phase investment across Dunkirk, Bosquel and Bouchain; not Bouchain-specific project financing.
SoftBank Group Corp. (Sponsor)
Sources (1)
Financing record 104; claim-specific source links appear in the exhibit sources where published.