Scope and capacity
Building A is the completed first facility at SDC Austin and was reported fully leased by early 2026. It includes space prepared for TACC's Leadership-Class Computing Facility.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (4)
Milestone construction complete · Building A completed
Actual · Sabey Austin Building A (Project)
Claim 47503 · Recorded claim type: Actual · Review: Approved · Claim date: Oct 17, 2024
- Sabey Data Centers completes construction at Austin, Texas data center site
Sabey Data Centers · Document date: Oct 17, 2024 · Primary
Source reference: SRC-7017 · Company announcement · Recorded authority: Party primary
Source URL
https://sabeydatacenters.com/news/sabey-data-centers-completes-construction-at-austin-texas-data-center-site
https://sabeydatacenters.com/news/sabey-data-centers-completes-construction-at-austin-texas-data-center-site
Batch 28 — Assertions
Document date: Not stated · Primary
Source reference: SRC-2607
No public source link
Milestone customer commitment · TACC selects SDC Austin for Horizon/LCCF
Actual · Sabey Austin Building A (Project)
Claim 47504 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 23, 2024
- TACC selects Sabey Data Centers in Round Rock as colocation partner for new supercomputer
Texas Advanced Computing Center · Document date: Aug 23, 2024 · Primary
Source reference: SRC-7020 · Company announcement · Recorded authority: Official primary
Source URL
https://tacc.utexas.edu/news/latest-news/2024/08/23/tacc-selects-sabey-data-centers-in-round-rock-as-colocation-partner-for-new-supercomputer/
https://tacc.utexas.edu/news/latest-news/2024/08/23/tacc-selects-sabey-data-centers-in-round-rock-as-colocation-partner-for-new-supercomputer/
Batch 28 — Assertions
Document date: Not stated · Primary
Source reference: SRC-2607
No public source link
Milestone commissioning · 15 MW initial LCCF space passes full power testing
Actual · Sabey Austin Building A (Project)
Claim 47505 · Recorded claim type: Actual · Review: Approved · Claim date: Feb 28, 2026
- New LCCF datacenter nears completion
Texas Advanced Computing Center · Document date: Mar 1, 2026 · Primary
Source reference: SRC-7021 · Company announcement · Recorded authority: Official primary
Source URL
https://lccf.tacc.utexas.edu/construction-updates/2026/new-lccf-datacenter-nears-completion/
https://lccf.tacc.utexas.edu/construction-updates/2026/new-lccf-datacenter-nears-completion/
Batch 28 — Assertions
Document date: Not stated · Primary
Source reference: SRC-2607
No public source link
Milestone tenant deployment · Horizon GPU phase operational; CPU phase follows
Actual · Sabey Austin Building A (Project)
Claim 47506 · Recorded claim type: Actual · Review: Approved · Claim date: Jul 7, 2026
- Opening the future of science — Leadership-Class Computing arrives
Texas Advanced Computing Center · Document date: Jul 7, 2026 · Primary
Source reference: SRC-7022 · Company announcement · Recorded authority: Official primary
Source URL
https://tacc.utexas.edu/news/latest-news/2026/07/07/opening-the-future-of-science/
https://tacc.utexas.edu/news/latest-news/2026/07/07/opening-the-future-of-science/
Batch 28 — Assertions
Document date: Not stated · Primary
Source reference: SRC-2607
No public source link
Counterparties and capital
Texas Advanced Computing Center · Customer · CMP-1224
The University of Texas at Austin · Customer · CMP-1225
U.S. National Science Foundation · Government authority · CMP-1226