Riot Rockdale AI Data Center Campus

Rockdale, Texas, United StatesPartially operational
Capacity
191 MW
Contracted
Lead participant
Riot Platforms
Operator
Last updated
Aug 27, 2026
Most recent public record update

About Riot Rockdale AI Data Center Campus

Riot is converting its Rockdale campus into a contracted AI data center platform. A new 20-year lease covers 191 MW of critical IT capacity, alongside an earlier AMD deployment. Riot Platforms, Morgan Stanley is associated with the development in Rockdale, Milam County, TX, US. The disclosed development scope includes 191 MW contracted critical IT; initial 96 MW expected December 2027; full delivery expected June 2028. Power and physical infrastructure include existing approved and energized interconnection supports phased build-to-suit delivery. Riot executed a 20-year lease for 191 MW of critical IT capacity. Riot disclosed a Morgan Stanley interim financing facility of up to $573 million for the 191 MW build-to-suit program.

Capacity

Contracted
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Contracted Supply191 MWActual · Riot Rockdale AI Data Center Campus
Contracted Supply191 MWActual · Riot Rockdale AI Data Center Campus

Development

1 phases · 2 milestones
Operating and expansion programPartially Operational

Project-wide phase for Riot Rockdale AI Data Center Campus; capacity class is contracted supply.

Aug 10, 2026
Riot Rockdale AI Build-to-Suit development disclosed
Completed
Initial AI capacity operating; 191 MW build-to-suit contracted for phased delivery
Forecast

Infrastructure

Electric GridPartially Operational

191 MW

Riot executed a 20-year lease for 191 MW of critical IT capacity.

Site FacilityPartially Operational

Existing approved and energized interconnection supports phased build-to-suit delivery.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
Riot campus | Rockdale | Milam County | Texas
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
191 MW
Actual
Capacity Basis
Riot executed a 20-year lease for 191 MW of critical IT capacity.
Actual
Location Context
Riot campus | Rockdale | Milam County | Texas
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
191 MW
Actual
Capacity Basis
Riot executed a 20-year lease for 191 MW of critical IT capacity.
Actual
Development Scale
191 MW contracted critical IT
Actual
Development Milestone
Initial 96 MW expected December 2027
Actual
Power Arrangement
Full delivery expected June 2028.
Actual
Site Configuration
Riot campus | Rockdale | Milam County | Texas
Actual