Skip to content

Raxio MZ1 Maputo

Beluluane Industrial Park, Matola, L, MozambiqueOperating
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Raxio MZ1 is an operating, carrier-neutral Tier III data center in Matola with a current specification of 3 MW IT power.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Current operating configurationOperational

1 building

Expansion/definition transition date is not disclosed.

Original announced configurationChanged or cancelled

1 building

Historical plan retained; not current operating capacity.

Milestones (2)
MZ1 construction groundbreaking

Sep 30, 2022 · Recorded actual event

Completed · Construction started

Source not linked
Raxio launched MZ1

May 28, 2024 · Recorded actual event

Completed · Commercial operation

Source not linked

Participants

Raxio Group

Operator

Sources by role
Other participants (1)
Uptime Institute

Contractor

Sources by role

Additional project facts

Project identity

Source report

Raxio MZ1 Maputo

Source

Infrastructure & permits

Technical details (2)
Electric grid

Operational

3 MW IT

Current operator specification; supersedes the early plan as current state.

Fiber

Operational

2 diverse intakes

Two fiber intakes/diverse routes and two meet-me rooms; providers not individually disclosed.