Raxio Angola AO1

Cacuaco, AngolaOperating
Evidence
Planned critical IT
7 MW
Updated
Oct 28, 2026

Raxio Angola AO1 is a single modular carrier-neutral facility; 3 MW opening scope remains distinct from 7 MW full design.

Capacity

Opening IT capacity

Planned / design or future potential

3 MW

Source

Current full design IT capacity

Planned / design or future potential

7 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Opening configurationOperational

1 building

Up to 3 MW IT at October 2025 opening.

Full modular designAnnounced or preconstruction

1 building

Current technical sheet markets up to 7 MW IT.

Milestones (2)
Foundation stone laid

Sep 21, 2023 · Recorded actual event

Completed · Construction started

Source not linked
AO1 opened at up to 3 MW IT

Oct 2, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked

Participants

Meridiam

Investor

Sources by role
Investor (1)
Raxio Angola LDA

Owner

Sources by role
Owner (1)
Owner (1)
Raxio Group

Operator

Sources by role
Operator (1)
Operator (1)
Other participants (1)
Uptime Institute

Contractor

Sources by role
Contractor (1)

Capital & incentives

Capital claims

Announced facility investment

Source report

$30 million

Source

Regional financing allocated to ao1

Source report

False

Source

Site & development

Facility area

Source report

4,000 square metres

Source

Subsea landing proximity

Source report

True

Source

Technical specifications

Current rack capacity

Source report

800 racks

Source

Opening rack statement

Source report

800 racks+

Source

Additional project facts

Commissioned date

Actual

2025-10-02

Source

Carrier neutral

Source report

True

Source

Tier standard claim

Source report

Tier III

Source

Terrestrial connectivity role

Source report

True

Source

Live utilized IT load disclosed

Source report

False

Source

Full design equals opening capacity

Source report

False

Source

Infrastructure & permits

Technical details (1)
Fiber

Operational

Carrier-neutral facility near terrestrial routes and submarine landing infrastructure; carrier list not published on reviewed page.

Public-source research. Plans may change. See Evidence for sources and qualifications.