Racks Central RCJM Johor AI Factory Campus

Pasir Gudang, Johor, MalaysiaUnder construction
Evidence
Contracted
70 MW
Updated
Oct 28, 2026

Racks Central is building the RCJM AI Factory Campus in Pasir Gudang, Johor. The first facility is fully committed for 70 MW of IT load, while the combined campus plan reaches 510 MW. Racks Central is associated with the development in Pasir Gudang, Johor, MY. The disclosed development scope includes 70 MW committed IT load in RCJM1; 510 MW combined campus design; first service targeted Q1 2027. Power and physical infrastructure include high-density AI campus with a phased Johor delivery program. Racks Central states RCJM1 is fully committed for 70 MW of IT load.

Capacity

Reported capacity

Actual

70 MW

Source

Reported capacity

Actual

70 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Construction programUnder construction

Project-wide phase for Racks Central RCJM Johor AI Factory Campus; capacity class is contracted supply.

Milestones (2)
RCJM Pasir Gudang Campus development disclosed

Aug 12, 2026 · Recorded actual event

Completed · Announced

Source not linked
Construction milestone reached; first phase committed

Date not disclosed · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Racks Central

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

RCJM campus | Pasir Gudang | Johor | Malaysia

Source

Location context

Actual

RCJM campus | Pasir Gudang | Johor | Malaysia

Source

Development scale

Actual

70 MW committed IT load in RCJM1

Source

Development milestone

Actual

510 MW combined campus design

Source

Site configuration

Actual

RCJM campus | Pasir Gudang | Johor | Malaysia

Source

Technical specifications

Power arrangement

Actual

First service targeted Q1 2027.

Source

Additional project facts

Lifecycle status

Actual

Construction

Source

Capacity basis

Actual

Racks Central states RCJM1 is fully committed for 70 MW of IT load.

Source

Lifecycle status

Actual

Construction

Source

Capacity basis

Actual

Racks Central states RCJM1 is fully committed for 70 MW of IT load.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

70 MW

Racks Central states RCJM1 is fully committed for 70 MW of IT load.

Site facility

Planned or represented

High-density AI campus with a phased Johor delivery program.

Public-source research. Plans may change. See Evidence for sources and qualifications.