Cartis diligence evidence schedule
Quantum Loophole Frederick Campus
PRJ-1084 · Site · Adamstown, Maryland, United States
Record last updated Oct 28, 2026
Scope and capacity
On September 14, 2026, Frederick County rejected the Catellus development-rights and community-benefits agreement application and extended its pause on new data-center applications to July 1, 2027. These actions do not amount to cancellation of all previously approved parcels or the entire Frederick campus. Quantum Loophole’s Frederick campus is a large-scale data-center development area in Adamstown, Maryland, planned around dedicated fiber, power and shared infrastructure. Public materials describe a multi-tenant campus opportunity extending toward approximately 2.8 GW at full build, but phase-by-phase power delivery and tenant occupancy remain prospective. The figure is a design ceiling, not operating IT load. Local land-use conditions, transmission upgrades, environmental permits, tenants and construction financing remain material execution items.
Headline: 2,800 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (10)
Location context · Quantum Loophole Frederick Campus | Adamstown | Maryland | US
Actual · Quantum Loophole Frederick Campus (Project)
Claim 70308 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Quantum Loophole Frederick Campus public-record research record
PoweredByWho · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4007 · News report · Recorded authority: Secondary
Source URL
https://poweredbywho.com/rankings/largest-data-centers-under-construction
https://poweredbywho.com/rankings/largest-data-centers-under-construction
Lifecycle status · Preconstruction
Actual · Quantum Loophole Frederick Campus (Project)
Claim 70309 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Quantum Loophole Frederick Campus public-record research record
PoweredByWho · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4007 · News report · Recorded authority: Secondary
Source URL
https://poweredbywho.com/rankings/largest-data-centers-under-construction
https://poweredbywho.com/rankings/largest-data-centers-under-construction
Reported capacity · 2,800 MW
Planned / design or future potential · Quantum Loophole Frederick Campus (Project)
Claim 70310 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Quantum Loophole Frederick Campus public-record research record
PoweredByWho · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4007 · News report · Recorded authority: Secondary
Source URL
https://poweredbywho.com/rankings/largest-data-centers-under-construction
https://poweredbywho.com/rankings/largest-data-centers-under-construction
Capacity basis · 2,800 MW future full build site capacity; not measured operating IT load.
Actual · Quantum Loophole Frederick Campus (Project)
Claim 70311 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Quantum Loophole Frederick Campus public-record research record
PoweredByWho · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4007 · News report · Recorded authority: Secondary
Source URL
https://poweredbywho.com/rankings/largest-data-centers-under-construction
https://poweredbywho.com/rankings/largest-data-centers-under-construction
Location context · Quantum Loophole Frederick Campus | Adamstown | Maryland | US
Actual · Quantum Loophole Frederick Campus (Project)
Claim 74486 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Quantum Loophole Frederick Campus public-record research record
PoweredByWho · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4007 · News report · Recorded authority: Secondary
Source URL
https://poweredbywho.com/rankings/largest-data-centers-under-construction
https://poweredbywho.com/rankings/largest-data-centers-under-construction
Lifecycle status · Preconstruction
Actual · Quantum Loophole Frederick Campus (Project)
Claim 74487 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Quantum Loophole Frederick Campus public-record research record
PoweredByWho · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4007 · News report · Recorded authority: Secondary
Source URL
https://poweredbywho.com/rankings/largest-data-centers-under-construction
https://poweredbywho.com/rankings/largest-data-centers-under-construction
Reported capacity · 2,800 MW
Planned / design or future potential · Quantum Loophole Frederick Campus (Project)
Claim 74488 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Quantum Loophole Frederick Campus public-record research record
PoweredByWho · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4007 · News report · Recorded authority: Secondary
Source URL
https://poweredbywho.com/rankings/largest-data-centers-under-construction
https://poweredbywho.com/rankings/largest-data-centers-under-construction
Capacity basis · Approximately 2,800 MW is a prospective full build campus ceiling, not operating capacity.
Actual · Quantum Loophole Frederick Campus (Project)
Claim 74489 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Quantum Loophole Frederick Campus public-record research record
PoweredByWho · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4007 · News report · Recorded authority: Secondary
Source URL
https://poweredbywho.com/rankings/largest-data-centers-under-construction
https://poweredbywho.com/rankings/largest-data-centers-under-construction
Development model · Multi tenant powered land campus
Actual · Quantum Loophole Frederick Campus (Project)
Claim 74490 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Quantum Loophole Frederick campus
Quantum Loophole · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4230 · Company announcement · Recorded authority: Party primary
Source URL
https://quantumloophole.com/frederick-maryland/
https://quantumloophole.com/frederick-maryland/
Capacity status · Phased design ceiling; no operating load claimed
Actual · Quantum Loophole Frederick Campus (Project)
Claim 74492 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Quantum Loophole Frederick campus
Quantum Loophole · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4230 · Company announcement · Recorded authority: Party primary
Source URL
https://quantumloophole.com/frederick-maryland/
https://quantumloophole.com/frederick-maryland/
Counterparties and capital
Quantum Loophole · Developer · CMP-0746
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.