QTS Van Wert Data Center Campus

Van Wert, Ohio, United StatesProposed
Capacity
500 MW
Planned / design
Lead participant
QTS Data Centers
Developer
Last updated
Aug 28, 2026
Most recent public record update

About QTS Van Wert Data Center Campus

QTS plans a seven-building data center campus on roughly 902 acres in Van Wert, Ohio. The company describes a five-to-six-year build program, investment of up to $10 billion, closed-loop cooling, and privately funded energy infrastructure developed with AEP Ohio.

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential500 MWDesign · QTS Van Wert Data Center Campus

Development

1 phases · 1 milestones
Planned phased campusAnnounced Or Preconstruction

QTS plans a seven-building data center campus on roughly 902 acres in Van Wert, Ohio. The company describes a five-to-six-year build program, investment of up to $10 billion, closed-loop cooling, and privately funded energy infrastructure developed with AEP Ohio.

7 buildings

May 29, 2026
QTS and the City of Van Wert announced the campus
Completed

Infrastructure

Cooling SystemPotential Or Planned

Closed-loop cooling designed not to consume cooling water once operational.

Electric GridPotential Or Planned

500 MW

QTS/AEP planning boundary; project-specific infrastructure is to be privately funded.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

8 facts
Location Context
QTS Van Wert Data Center Campus | Van Wert | Ohio | US
Actual
Lifecycle Status
Proposed
Actual
Reported Capacity
500 MW
Design
Capacity Basis
500 MW future full build site capacity; not measured operating IT load. QTS confirms the campus, but the 500 MW figure remains a public record tracked future design boundary.
Actual
Site Area
902 acres
Actual
Building Count
7
Actual
Reported Investment
$10,000,000,000
Reported Rounded
Construction Duration
5–6 Years
Actual