QTS RIC1 Richmond Data Center Campus

PRJ-0870 · Site · Sandston, Virginia, United States

Record last updated Oct 28, 2026

Scope and capacity

QTS RIC1 Richmond Data Center Campus, also known as QTS Richmond 1, is a partially operational data center campus in Sandston, VA, US associated with QTS Data Centers. 100-acre QTS location; 240 MW+ published campus capacity.

Headline: 240 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (22)

Location context · QTS Richmond 1 | Sandston | VA | US

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 63377 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Richmond 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3540 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Operational

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 63378 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Richmond 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3540 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 240 MW

Design · QTS RIC1 Richmond Data Center Campus (Project)

Claim 63379 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. QTS data center portfolio — Richmond 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3540 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · QTS Data Centers publishes 240 MW of critical IT capacity for this record boundary.

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 63380 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Richmond 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3540 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Location context · QTS Richmond 1 | Sandston | VA | US

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 93065 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Richmond 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3540 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Operating

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 93066 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Richmond 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3540 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 240 MW

Planned / design or future potential · QTS RIC1 Richmond Data Center Campus (Project)

Claim 93067 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center portfolio — Richmond 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3540 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · 240 MW facility or campus design capacity.

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 93068 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Richmond 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3540 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Project boundary · QTS Richmond 1

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 93070 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · Sandston, VA, US

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 93071 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Lifecycle status · Operating

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 93072 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Capacity basis · 240 MW facility or campus design capacity.

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 93073 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · QTS Richmond 1 location | Sandston | VA | United States

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104097 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5762 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104098 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5762 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 240 MW

Planned / design or future potential · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104099 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5762 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Capacity basis · 240 MW facility or campus IT design capacity.

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104100 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5762 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 240 MW

Planned / design or future potential · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104101 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5762 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Project identity · QTS Richmond 1

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104102 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. White Oak transmission application

    Dominion Energy Virginia / Virginia SCC · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-5764 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.dominionenergy.com/-/media/content/about/power-line-projects/white-oak/pdfs/application-volume-3of3-part1of2-2023-white-oak.pdf

Location context · Sandston, VA, US

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104103 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. White Oak transmission application

    Dominion Energy Virginia / Virginia SCC · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-5764 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.dominionenergy.com/-/media/content/about/power-line-projects/white-oak/pdfs/application-volume-3of3-part1of2-2023-white-oak.pdf

Lifecycle status · Partially operational

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104104 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. White Oak transmission application

    Dominion Energy Virginia / Virginia SCC · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-5764 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.dominionenergy.com/-/media/content/about/power-line-projects/white-oak/pdfs/application-volume-3of3-part1of2-2023-white-oak.pdf

Development detail · 100-Acre QTS location; 240 MW+ published campus capacity.

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104105 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. White Oak transmission application

    Dominion Energy Virginia / Virginia SCC · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-5764 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.dominionenergy.com/-/media/content/about/power-line-projects/white-oak/pdfs/application-volume-3of3-part1of2-2023-white-oak.pdf

Capacity basis · 240 MW facility or campus IT design capacity.

Actual · QTS RIC1 Richmond Data Center Campus (Project)

Claim 104106 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. White Oak transmission application

    Dominion Energy Virginia / Virginia SCC · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-5764 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.dominionenergy.com/-/media/content/about/power-line-projects/white-oak/pdfs/application-volume-3of3-part1of2-2023-white-oak.pdf

Counterparties and capital

Dominion Energy Virginia · Utility provider · CMP-1595

QTS Data Centers · Developer · CMP-0368