Skip to content
All records
Data center siteSite record

QTS Prince William Digital Gateway Campus

Gainesville, Virginia, United StatesStatus Under Review
Capacity
No public figure
Lead participant
GW Acquisition Co. LLC / GW Acquisition I LLC
Developer
Last updated
Aug 25, 2026
Most recent public record update

About QTS Prince William Digital Gateway Campus

QTS Prince William Digital Gateway Campus — QTS/GW Acquisition development comprising Digital Gateway North and South rezoning areas. QTS Prince William Digital Gateway Campus is in Gainesville, VA, US and is a data center campus with canceled status. Participants include GW Acquisition Co. LLC / GW Acquisition I LLC as developer, QTS Data Centers as developer. Development comprises Digital Gateway North (canceled), Digital Gateway South (canceled). Key milestones include QTS terminated project and withdrew filings. (2026-07-02). Permitting includes rezoning rEZ2022-00032 for Digital Gateway North (void) and rezoning rEZ2022-00033 for Digital Gateway South (void).

Program relationships

1 linked

Projects sharing a market, utility, or organization.

4 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

2 phases · 1 milestones
Digital Gateway NorthStatus Not Disclosed

REZ2022-00032.

Digital Gateway SouthStatus Not Disclosed

REZ2022-00033.

Jul 2, 2026
QTS terminated project and withdrew filings
Completed

Infrastructure

No public infrastructure records are attached.

Project map

0 of 1 project point mapped
Infrastructure facts
0
Mapped records
0
Capacity figures
0

No map point available

Facts & sources

Published claims and their source links.

1 facts
Project Status
Terminated and associated filings withdrawn
Fact