Cartis diligence evidence schedule

QTS Fort Worth Data Center Campus

PRJ-0914 · Site · Fort Worth, Texas, United States

Record last updated Oct 28, 2026

Scope and capacity

QTS Fort Worth Data Center Campus, also known as QTS Fort Worth, is a partially operational data center campus in Fort Worth, TX, US associated with QTS Data Centers. 52-acre QTS location; 70 MW+ published campus capacity. Large QTS campus with dedicated electrical infrastructure; QTS separately describes further gross buildout potential, which is not used as the headline value here.

Headline: 70 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (22)

Location context · QTS Fort Worth | Fort Worth | TX | US

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 64228 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Fort Worth

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3618 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 64229 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Fort Worth

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3618 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 70 MW

Design · QTS Fort Worth Data Center Campus (Project)

Claim 64230 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. QTS data center portfolio — Fort Worth

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3618 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · QTS Data Centers publishes 70 MW of critical IT capacity for this record boundary.

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 64231 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Fort Worth

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3618 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Location context · QTS Fort Worth | Fort Worth | TX | US

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 93459 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Fort Worth

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3618 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 93460 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Fort Worth

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3618 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 70 MW

Planned / design or future potential · QTS Fort Worth Data Center Campus (Project)

Claim 93461 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center portfolio — Fort Worth

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3618 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · 70 MW facility or campus design capacity.

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 93462 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Fort Worth

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3618 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Project boundary · QTS Fort Worth

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 93464 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · Fort Worth, TX, US

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 93465 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Lifecycle status · Partially operational

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 93466 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Capacity basis · 70 MW facility or campus design capacity.

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 93467 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · QTS Fort Worth location | Fort Worth | TX | United States

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 104191 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5797 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 104192 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5797 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 70 MW

Planned / design or future potential · QTS Fort Worth Data Center Campus (Project)

Claim 104193 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5797 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Capacity basis · 70 MW facility or campus IT design capacity.

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 104194 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5797 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 70 MW

Planned / design or future potential · QTS Fort Worth Data Center Campus (Project)

Claim 104195 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5797 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Project identity · QTS Fort Worth

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 104196 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS Fort Worth redevelopment presentation

    City of Fort Worth · Document date: Mar 26, 2019 · Primary

    Source reference: SRC-5799 · Government record · Recorded authority: Official primary

    Source URL

    https://fortworthgov.granicus.com/MetaViewer.php?clip_id=3150&meta_id=360249&view_id=2

Location context · Fort Worth, TX, US

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 104197 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS Fort Worth redevelopment presentation

    City of Fort Worth · Document date: Mar 26, 2019 · Primary

    Source reference: SRC-5799 · Government record · Recorded authority: Official primary

    Source URL

    https://fortworthgov.granicus.com/MetaViewer.php?clip_id=3150&meta_id=360249&view_id=2

Lifecycle status · Partially operational

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 104198 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS Fort Worth redevelopment presentation

    City of Fort Worth · Document date: Mar 26, 2019 · Primary

    Source reference: SRC-5799 · Government record · Recorded authority: Official primary

    Source URL

    https://fortworthgov.granicus.com/MetaViewer.php?clip_id=3150&meta_id=360249&view_id=2

Development detail · 52-Acre QTS location; 70 MW+ published campus capacity.

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 104199 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS Fort Worth redevelopment presentation

    City of Fort Worth · Document date: Mar 26, 2019 · Primary

    Source reference: SRC-5799 · Government record · Recorded authority: Official primary

    Source URL

    https://fortworthgov.granicus.com/MetaViewer.php?clip_id=3150&meta_id=360249&view_id=2

Capacity basis · 70 MW facility or campus IT design capacity.

Actual · QTS Fort Worth Data Center Campus (Project)

Claim 104200 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS Fort Worth redevelopment presentation

    City of Fort Worth · Document date: Mar 26, 2019 · Primary

    Source reference: SRC-5799 · Government record · Recorded authority: Official primary

    Source URL

    https://fortworthgov.granicus.com/MetaViewer.php?clip_id=3150&meta_id=360249&view_id=2

Counterparties and capital

QTS Data Centers · Developer · CMP-0368