Cartis diligence evidence schedule

QTS DFW1 Irving Data Center Campus

PRJ-0871 · Site · Irving, Texas, United States

Record last updated Oct 28, 2026

Scope and capacity

QTS DFW1 Irving Data Center Campus, also known as QTS Irving, is a partially operational data center campus in Irving, TX, US associated with QTS Data Centers. 56-acre QTS location; 165 MW+ published campus capacity.

Headline: 165 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (22)

Location context · QTS Irving | Irving | TX | US

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 63381 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Irving

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3541 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 63382 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Irving

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3541 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 165 MW

Design · QTS DFW1 Irving Data Center Campus (Project)

Claim 63383 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. QTS data center portfolio — Irving

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3541 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · QTS Data Centers publishes 165 MW of critical IT capacity for this record boundary.

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 63384 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Irving

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3541 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Location context · QTS Irving | Irving | TX | US

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 93074 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Irving

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3541 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 93075 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Irving

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3541 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 165 MW

Planned / design or future potential · QTS DFW1 Irving Data Center Campus (Project)

Claim 93076 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center portfolio — Irving

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3541 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · 165 MW facility or campus design capacity.

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 93077 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Irving

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3541 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Project boundary · QTS Irving

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 93079 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · Irving, TX, US

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 93080 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Lifecycle status · Partially operational

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 93081 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Capacity basis · 165 MW facility or campus design capacity.

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 93082 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · QTS Irving location | Irving | TX | United States

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 104125 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5772 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 104126 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5772 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 165 MW

Planned / design or future potential · QTS DFW1 Irving Data Center Campus (Project)

Claim 104127 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5772 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Capacity basis · 165 MW facility or campus IT design capacity.

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 104128 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5772 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 165 MW

Planned / design or future potential · QTS DFW1 Irving Data Center Campus (Project)

Claim 104129 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5772 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Project identity · QTS Irving

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 104130 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. City of Irving data-center standards

    City of Irving · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5774 · Government record · Recorded authority: Official primary

    Source URL

    https://irvingtx.gov/data-centers

Location context · Irving, TX, US

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 104131 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. City of Irving data-center standards

    City of Irving · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5774 · Government record · Recorded authority: Official primary

    Source URL

    https://irvingtx.gov/data-centers

Lifecycle status · Partially operational

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 104132 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. City of Irving data-center standards

    City of Irving · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5774 · Government record · Recorded authority: Official primary

    Source URL

    https://irvingtx.gov/data-centers

Development detail · 56-Acre QTS location; 165 MW+ published campus capacity.

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 104133 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. City of Irving data-center standards

    City of Irving · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5774 · Government record · Recorded authority: Official primary

    Source URL

    https://irvingtx.gov/data-centers

Capacity basis · 165 MW facility or campus IT design capacity.

Actual · QTS DFW1 Irving Data Center Campus (Project)

Claim 104134 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. City of Irving data-center standards

    City of Irving · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5774 · Government record · Recorded authority: Official primary

    Source URL

    https://irvingtx.gov/data-centers

Counterparties and capital

QTS Data Centers · Developer · CMP-0368