Cartis diligence evidence schedule

QTS Denver Data Center Campus

PRJ-0909 · Site · Aurora, Colorado, United States

Record last updated Oct 28, 2026

Scope and capacity

QTS Denver Data Center Campus, also known as QTS Denver, is a construction data center campus in Aurora, CO, US associated with QTS Data Centers. 65-acre QTS location; 160 MW+ published campus capacity. 160 MW+ is the planned Aurora campus design, not operating IT load; construction and air-permit milestones remain phase-specific.

Headline: 160 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (20)

Location context · QTS Denver | Aurora | CO | US

Actual · QTS Denver Data Center Campus (Project)

Claim 64208 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Denver

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3612 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS Denver Data Center Campus (Project)

Claim 64209 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Denver

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3612 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 160 MW

Design · QTS Denver Data Center Campus (Project)

Claim 64210 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. QTS data center portfolio — Denver

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3612 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · QTS Data Centers publishes 160 MW of critical IT capacity for this record boundary.

Actual · QTS Denver Data Center Campus (Project)

Claim 64211 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Denver

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3612 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Location context · QTS Denver | Aurora | CO | US

Actual · QTS Denver Data Center Campus (Project)

Claim 93414 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Denver

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3612 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS Denver Data Center Campus (Project)

Claim 93415 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Denver

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3612 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 160 MW

Planned / design or future potential · QTS Denver Data Center Campus (Project)

Claim 93416 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center portfolio — Denver

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3612 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · 160 MW facility or campus design capacity.

Actual · QTS Denver Data Center Campus (Project)

Claim 93417 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Denver

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3612 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Project boundary · QTS Denver

Actual · QTS Denver Data Center Campus (Project)

Claim 93419 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · Aurora, CO, US

Actual · QTS Denver Data Center Campus (Project)

Claim 93420 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Lifecycle status · Partially operational

Actual · QTS Denver Data Center Campus (Project)

Claim 93421 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Capacity basis · 160 MW facility or campus design capacity.

Actual · QTS Denver Data Center Campus (Project)

Claim 93422 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · QTS Denver location | Aurora | CO | United States

Actual · QTS Denver Data Center Campus (Project)

Claim 104135 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5776 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Lifecycle status · Construction

Actual · QTS Denver Data Center Campus (Project)

Claim 104136 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5776 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 160 MW

Planned / design or future potential · QTS Denver Data Center Campus (Project)

Claim 104137 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5776 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Capacity basis · 160 MW+ is the planned Aurora campus design, not operating IT load; construction and air permit milestones remain phase specific.

Actual · QTS Denver Data Center Campus (Project)

Claim 104138 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5776 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Future IT design · 160+ MW

Planned / design or future potential · QTS Denver Data Center Campus (Project)

Claim 104139 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5776 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Site area · 65 acres

Actual · QTS Denver Data Center Campus (Project)

Claim 104140 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS Aurora development application

    Adams County · Document date: Oct 1, 2025 · Primary

    Source reference: SRC-5778 · Government record · Recorded authority: Official primary

    Source URL

    https://adamscountyco.gov/wp-content/uploads/2025/10/RCU2024-00010-submittal2.pdf

Planned backup generators · 98 generators

Forecast · QTS Denver Data Center Campus (Project)

Claim 104141 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

  1. QTS Aurora development application

    Adams County · Document date: Oct 1, 2025 · Primary

    Source reference: SRC-5778 · Government record · Recorded authority: Official primary

    Source URL

    https://adamscountyco.gov/wp-content/uploads/2025/10/RCU2024-00010-submittal2.pdf

Lifecycle · Development and permitting

Actual · QTS Denver Data Center Campus (Project)

Claim 104142 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS Aurora development application

    Adams County · Document date: Oct 1, 2025 · Primary

    Source reference: SRC-5778 · Government record · Recorded authority: Official primary

    Source URL

    https://adamscountyco.gov/wp-content/uploads/2025/10/RCU2024-00010-submittal2.pdf

Counterparties and capital

QTS Data Centers · Developer · CMP-0368

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.