Cartis diligence evidence schedule

QTS Chicago Data Center Campus

PRJ-0910 · Site · Chicago, Illinois, United States

Record last updated Oct 28, 2026

Scope and capacity

QTS Chicago Data Center Campus, also known as QTS Chicago, is a partially operational data center campus in Chicago, IL, US associated with QTS Data Centers. 30-acre QTS location; 95 MW+ published campus capacity.

Headline: 95 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (22)

Location context · QTS Chicago | Chicago | IL | US

Actual · QTS Chicago Data Center Campus (Project)

Claim 64212 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Chicago

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3613 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS Chicago Data Center Campus (Project)

Claim 64213 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Chicago

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3613 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 95 MW

Design · QTS Chicago Data Center Campus (Project)

Claim 64214 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. QTS data center portfolio — Chicago

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3613 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · QTS Data Centers publishes 95 MW of critical IT capacity for this record boundary.

Actual · QTS Chicago Data Center Campus (Project)

Claim 64215 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Chicago

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3613 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Location context · QTS Chicago | Chicago | IL | US

Actual · QTS Chicago Data Center Campus (Project)

Claim 93423 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Chicago

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3613 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS Chicago Data Center Campus (Project)

Claim 93424 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Chicago

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3613 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 95 MW

Planned / design or future potential · QTS Chicago Data Center Campus (Project)

Claim 93425 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center portfolio — Chicago

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3613 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · 95 MW facility or campus design capacity.

Actual · QTS Chicago Data Center Campus (Project)

Claim 93426 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Chicago

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3613 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Project boundary · QTS Chicago

Actual · QTS Chicago Data Center Campus (Project)

Claim 93428 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · Chicago, IL, US

Actual · QTS Chicago Data Center Campus (Project)

Claim 93429 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Lifecycle status · Partially operational

Actual · QTS Chicago Data Center Campus (Project)

Claim 93430 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Capacity basis · 95 MW facility or campus design capacity.

Actual · QTS Chicago Data Center Campus (Project)

Claim 93431 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · QTS Chicago location | Chicago | IL | United States

Actual · QTS Chicago Data Center Campus (Project)

Claim 104143 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5779 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS Chicago Data Center Campus (Project)

Claim 104144 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5779 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 95 MW

Planned / design or future potential · QTS Chicago Data Center Campus (Project)

Claim 104145 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5779 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Capacity basis · 95 MW facility or campus IT design capacity.

Actual · QTS Chicago Data Center Campus (Project)

Claim 104146 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5779 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 95 MW

Planned / design or future potential · QTS Chicago Data Center Campus (Project)

Claim 104147 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5779 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Project identity · QTS Chicago

Actual · QTS Chicago Data Center Campus (Project)

Claim 104148 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. ComEd Elk Grove data-center transmission filing

    Illinois Commerce Commission · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-5781 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.icc.illinois.gov/docket/P2022-0486/documents/352005/files/615774.pdf

Location context · Chicago, IL, US

Actual · QTS Chicago Data Center Campus (Project)

Claim 104149 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. ComEd Elk Grove data-center transmission filing

    Illinois Commerce Commission · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-5781 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.icc.illinois.gov/docket/P2022-0486/documents/352005/files/615774.pdf

Lifecycle status · Partially operational

Actual · QTS Chicago Data Center Campus (Project)

Claim 104150 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. ComEd Elk Grove data-center transmission filing

    Illinois Commerce Commission · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-5781 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.icc.illinois.gov/docket/P2022-0486/documents/352005/files/615774.pdf

Development detail · 30-Acre QTS location; 95 MW+ published campus capacity.

Actual · QTS Chicago Data Center Campus (Project)

Claim 104151 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. ComEd Elk Grove data-center transmission filing

    Illinois Commerce Commission · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-5781 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.icc.illinois.gov/docket/P2022-0486/documents/352005/files/615774.pdf

Capacity basis · 95 MW facility or campus IT design capacity.

Actual · QTS Chicago Data Center Campus (Project)

Claim 104152 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. ComEd Elk Grove data-center transmission filing

    Illinois Commerce Commission · Document date: Jan 1, 2022 · Primary

    Source reference: SRC-5781 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.icc.illinois.gov/docket/P2022-0486/documents/352005/files/615774.pdf

Counterparties and capital

QTS Data Centers · Developer · CMP-0368

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.