Cartis diligence evidence schedule

QTS ASH1 Ashburn Data Center Campus

PRJ-0916 · Site · Ashburn, Virginia, United States

Record last updated Oct 28, 2026

Scope and capacity

QTS ASH1 Ashburn Data Center Campus, also known as QTS Ashburn 1, is a partially operational data center campus in Sterling, VA, US associated with QTS Data Centers. 28-acre QTS location; 55 MW+ published campus capacity.

Headline: 55 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (22)

Location context · QTS Ashburn 1 | Ashburn | VA | US

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 64236 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Ashburn 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3620 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 64237 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Ashburn 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3620 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 55 MW

Design · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 64238 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. QTS data center portfolio — Ashburn 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3620 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · QTS Data Centers publishes 55 MW of critical IT capacity for this record boundary.

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 64239 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Ashburn 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3620 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Location context · QTS Ashburn 1 | Ashburn | VA | US

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 93477 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Ashburn 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3620 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 93478 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Ashburn 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3620 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Reported capacity · 55 MW

Planned / design or future potential · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 93479 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center portfolio — Ashburn 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3620 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Capacity basis · 55 MW facility or campus design capacity.

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 93480 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center portfolio — Ashburn 1

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3620 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://qtsdatacenters.com/data-centers/

Project boundary · QTS Ashburn 1

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 93482 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · Ashburn, VA, US

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 93483 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Lifecycle status · Partially operational

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 93484 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Capacity basis · 55 MW facility or campus design capacity.

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 93485 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS compliance matrix

    QTS Data Centers · Document date: Mar 1, 2025 · Primary

    Source reference: SRC-4904 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/wp-content/uploads/2025/03/QTS_ComplianceMatrix.pdf

Location context · QTS Ashburn 1 location | Sterling | VA | United States

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104211 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5804 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Lifecycle status · Partially operational

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104212 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5804 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 55 MW

Planned / design or future potential · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104213 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5804 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Capacity basis · 55 MW facility or campus IT design capacity.

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104214 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5804 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Reported capacity · 55 MW

Planned / design or future potential · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104215 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. QTS data center locations directory

    QTS Data Centers · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-5804 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://q.com/data-centers/

Project identity · QTS Ashburn 1

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104216 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Northern Virginia data-center electric-project filing

    Virginia State Corporation Commission · Document date: Jan 1, 2025 · Primary

    Source reference: SRC-5806 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.scc.virginia.gov/docketsearch/DOCS/88qw01%21.PDF

Location context · Sterling, VA, US

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104217 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Northern Virginia data-center electric-project filing

    Virginia State Corporation Commission · Document date: Jan 1, 2025 · Primary

    Source reference: SRC-5806 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.scc.virginia.gov/docketsearch/DOCS/88qw01%21.PDF

Lifecycle status · Partially operational

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104218 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Northern Virginia data-center electric-project filing

    Virginia State Corporation Commission · Document date: Jan 1, 2025 · Primary

    Source reference: SRC-5806 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.scc.virginia.gov/docketsearch/DOCS/88qw01%21.PDF

Development detail · 28-Acre QTS location; 55 MW+ published campus capacity.

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104219 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Northern Virginia data-center electric-project filing

    Virginia State Corporation Commission · Document date: Jan 1, 2025 · Primary

    Source reference: SRC-5806 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.scc.virginia.gov/docketsearch/DOCS/88qw01%21.PDF

Capacity basis · 55 MW facility or campus IT design capacity.

Actual · QTS ASH1 Ashburn Data Center Campus (Project)

Claim 104220 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Northern Virginia data-center electric-project filing

    Virginia State Corporation Commission · Document date: Jan 1, 2025 · Primary

    Source reference: SRC-5806 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.scc.virginia.gov/docketsearch/DOCS/88qw01%21.PDF

Counterparties and capital

QTS Data Centers · Developer · CMP-0368

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.