Cartis diligence evidence schedule
QScale Q01 Campus
PRJ-0457 · Site · Lévis / Québec City area, Quebec, Canada
Captured 2026-09-06T04:12:47.495Z · Record last updated 2026-08-25
SHA-256: bb2202f0084c7308a78ed6bde63507302320c541ee0d1b8bd49e0bb05be59549
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
QScale Q01 Campus is one two-building AI/HPC campus; 142 MW campus power is a campus power figure.
Headline: 142 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Campus Power Capacity · 142 MW
Planned / design or future potential · QScale Q01 Campus (project)
Claim 43914 · Review: Approved · Claim date: Not published
Headline treatment: Selected headline
- HPE becomes first anchor tenant at Q01
QScale · Document date: 2023-05-22 · Primary
https://www.qscale.com/news/hewlett-packard-enterprise-hpe-q01-campus - QScale Q01 Campus
QScale · Document date: Not published · Primary
https://www.qscale.com/q01-campus
Accessible Power · 266 MVA
Source report · QScale Q01 Campus (project)
Claim 43915 · Review: Approved · Claim date: Not published
- QScale Q01 Campus
QScale · Document date: Not published · Primary
https://www.qscale.com/q01-campus
Building Count · 2
Source report · QScale Q01 Campus (project)
Claim 43916 · Review: Approved · Claim date: Not published
- QScale starts second Q01 building
Data Center Dynamics · Document date: 2026-06-05 · Primary
https://www.datacenterdynamics.com/en/news/canadas-qscale-breaks-ground-on-second-building-at-qu%C3%A9bec-campus/ - QScale begins construction of Q01 Building B
QScale · Document date: 2026-06-04 · Primary
https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure
Total Building Space · 930,000 square feet approx.
Source report · QScale Q01 Campus (project)
Claim 43917 · Review: Approved · Claim date: Not published
- QScale Q01 Campus
QScale · Document date: Not published · Primary
https://www.qscale.com/q01-campus
White Space Per Phase · 39,000 square feet approx.
Source report · QScale Q01 Campus (project)
Claim 43918 · Review: Approved · Claim date: Not published
- QScale Q01 Campus
QScale · Document date: Not published · Primary
https://www.qscale.com/q01-campus
Total White Space · 313,000 square feet approx.
Source report · QScale Q01 Campus (project)
Claim 43919 · Review: Approved · Claim date: Not published
- QScale Q01 Campus
QScale · Document date: Not published · Primary
https://www.qscale.com/q01-campus
Renewable Power Percent Marketed · 100 %
Source report · QScale Q01 Campus (project)
Claim 43920 · Review: Approved · Claim date: Not published
- QScale Q01 Campus
QScale · Document date: Not published · Primary
https://www.qscale.com/q01-campus
Tier Design · Tier 3 compliant design
Source report · QScale Q01 Campus (project)
Claim 43921 · Review: Approved · Claim date: Not published
- QScale Q01 Campus
QScale · Document date: Not published · Primary
https://www.qscale.com/q01-campus
Ocp Ready Recognition · True
Source report · QScale Q01 Campus (project)
Claim 43922 · Review: Approved · Claim date: Not published
- Q01 wins North American Data Center Project of the Year
QScale · Document date: 2023-12-06 · Primary
https://www.qscale.com/news/north-american-data-center-project-of-the-year-dcd-global-awards-2023-winner - Q01 becomes Canada's first OCP Ready colocation facility
QScale · Document date: 2022-12-15 · Primary
https://www.qscale.com/news/q01-first-ocp-ready-colocation-facility-in-canada
Campus First Anchor Tenant · Hewlett Packard Enterprise
Source report · QScale Q01 Campus (project)
Claim 43923 · Review: Approved · Claim date: Not published
- HPE becomes first anchor tenant at Q01
QScale · Document date: 2023-05-22 · Primary
https://www.qscale.com/news/hewlett-packard-enterprise-hpe-q01-campus
Platform Acquisition Closed · True
Source report · QScale Q01 Campus (project)
Claim 43924 · Review: Approved · Claim date: Not published
- Goldman Sachs Alternatives acquires QScale
Goldman Sachs Alternatives · Document date: 2026-05-13 · Primary
https://am.gs.com/en-us/advisors/news/press-release/2026/goldman-sachs-alternatives-acquire-qscale
Acquisition Consideration Disclosed · False
Source report · QScale Q01 Campus (project)
Claim 43925 · Review: Approved · Claim date: Not published
- Goldman Sachs Alternatives acquires QScale
Goldman Sachs Alternatives · Document date: 2026-05-13 · Primary
https://am.gs.com/en-us/advisors/news/press-release/2026/goldman-sachs-alternatives-acquire-qscale
Campus Operating It Load Disclosed · False
Source report · QScale Q01 Campus (project)
Claim 43926 · Review: Approved · Claim date: Not published
- HPE becomes first anchor tenant at Q01
QScale · Document date: 2023-05-22 · Primary
https://www.qscale.com/news/hewlett-packard-enterprise-hpe-q01-campus - QScale Q01 Campus
QScale · Document date: Not published · Primary
https://www.qscale.com/q01-campus
Building B Capacity Additive To Campus Power · False
Source report · QScale Q01 Campus (project)
Claim 43927 · Review: Approved · Claim date: Not published
- QScale begins construction of Q01 Building B
QScale · Document date: 2026-06-04 · Primary
https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure - QScale Q01 Campus
QScale · Document date: Not published · Primary
https://www.qscale.com/q01-campus
Counterparties and capital
Aligned Data Centers · Investor · CMP-0165
Goldman Sachs Alternatives · Owner · CMP-1128
Open Compute Project Foundation · Contractor · CMP-1138
QScale · Operator · CMP-1127
Amount not disclosed · 2023-06-30
Aligned strategic investment for future Q01 phases and other campuses; consideration undisclosed.
Aligned Data Centers (Investor) · QScale (Issuer Target)
Financing record 126; claim-specific source links appear in the exhibit sources where published.
Amount not disclosed · 2026-05-13
Goldman Sachs Alternatives acquired QScale with founders and management reinvesting; consideration undisclosed.
Goldman Sachs Alternatives (Acquirer Investor) · Macquarie Capital (Buyer Financial Advisor) · National Bank Capital Markets (Buyer Financial Advisor) · QScale (Target) · Scotiabank (Seller Financial Advisor) · TD Securities (Seller Financial Advisor)
Financing record 127; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.