Cartis diligence evidence schedule

QScale Q01 Building B

PRJ-0459 · Site · Lévis, Quebec, Canada

Record last updated Oct 28, 2026

Scope and capacity

QScale Q01 Building B is the second physical Q01 building; 60 MW IT and C$700m build are building-specific, not campus totals.

Headline: 60 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

IT capacity · 60 MW

Planned / design or future potential · QScale Q01 Building B (Project)

Claim 43935 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. QScale starts second Q01 building

    Data Center Dynamics · Document date: Jun 5, 2026 · Primary

    Source reference: SRC-2456 · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/canadas-qscale-breaks-ground-on-second-building-at-qu%C3%A9bec-campus/

  2. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

Investment estimate · CA$700 million

Source report · QScale Q01 Building B (Project)

Claim 43936 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

Construction status · Well underway

Source report · QScale Q01 Building B (Project)

Claim 43937 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

Maximum cabinet density · 600 kW+ per cabinet

Source report · QScale Q01 Building B (Project)

Claim 43938 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

AI hpc design · True

Source report · QScale Q01 Building B (Project)

Claim 43939 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

Operating capacity disclosed · False

Source report · QScale Q01 Building B (Project)

Claim 43940 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

Opening date disclosed · False

Source report · QScale Q01 Building B (Project)

Claim 43941 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

Tenant disclosed · False

Source report · QScale Q01 Building B (Project)

Claim 43942 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

Capacity is campus total · False

Source report · QScale Q01 Building B (Project)

Claim 43943 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

  2. QScale Q01 Campus

    QScale · Document date: Not stated · Primary

    Source reference: SRC-2446 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/q01-campus

Heat reuse intended · True

Source report · QScale Q01 Building B (Project)

Claim 43944 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. QScale begins construction of Q01 Building B

    QScale · Document date: Jun 4, 2026 · Primary

    Source reference: SRC-2447 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/q01-building-b-60mw-ai-ready-infrastructure

  2. QScale and Energir Development collaborate on waste heat recovery

    QScale · Document date: Mar 16, 2023 · Primary

    Source reference: SRC-2451 · Recorded authority: Party primary

    Source URL

    https://www.qscale.com/news/energir-vrt-waste-heat-recovery

Counterparties and capital

QScale · Operator · CMP-1127

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.