Data center siteSite record

Pure DC SJK01 Seinäjoki AI Campus

Seinäjoki / Kivenneva, FinlandUnder construction
Capacity
550 MW
Planned / design
Lead participant
SDC Ventures
Developer
Last updated
Aug 25, 2026
Most recent public record update

About Pure DC SJK01 Seinäjoki AI Campus

Pure DC is developing a 550 MW-plus AI campus in Seinäjoki. Its fully leased 110 MW first phase has secured EUR1.3 billion of senior debt and sits within a broader, permission-dependent buildout.

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design110 MWFact · Pure DC SJK01 Seinäjoki AI Campus
Design550 MWDesign · Pure DC SJK01 Seinäjoki AI Campus

Development

2 phases · 4 milestones
Phase 1Under Construction

110 MW first phase on the core lot; official city land sale record permits three data centers.

3 buildings

Full campus buildoutAnnounced Or Preconstruction

550 MW-plus future design across the wider campus.

Dec 1, 2025
Municipal zoning for the data center area completed
Completed
Apr 10, 2026
22.3-hectare core lot sold to Pure DC (FIN01) Projects Oy
Completed
Jul 14, 2026
110 MW Phase 1 and 550 MW-plus campus publicly launched
Completed
Jul 21, 2026
EUR1.3bn senior debt announced for Phase 1
Completed

Infrastructure

Electric GridSecured Or Contracted

700 MVA+

Access power for the full campus; not IT capacity.

Electric GridOperational

First substation is live while data center development continues.

Heat ReusePlanned Or Represented

Operator and city plan to reuse waste heat in district heating; a delivery contract has not been publicly disclosed.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 2Cooling & water: 1

Facts & sources

Published claims and their source links.

27 facts
Physical Campus Count
1 campus
Fact
Phase 1 It Capacity
110 MW
Fact
Phase 1 Lease Status
Fully leased
Fact
Phase 1 Investment Estimate
€1.50 billion+
Fact
Phase 1 Senior Debt
€1.30 billion
Fact
Phase 1 Planning Permissions Secured
True
Fact
Phase 1 Power Secured
True
Fact
Full Site Design Capacity Minimum
550 MW
Design
Full Site Capacity Is Operating Load
False
Fact
Accessible Power Minimum
700 MVA
Fact
Accessible Power Is It Capacity
False
Fact
Current Operator Campus Area
370 acres
Fact
Municipal Campus Area Approximate
150 hectares
Fact
Core Lot Area
22.3 hectares
Fact
Core Lot Purchase Price
€3,868,592
Fact
Core Lot Permitted Data Centers
3 data centers
Fact
Core Lot Equals Full Campus
False
Fact
First Substation Operational
True
Fact
First Data Hall Operational
False
Fact
Repeatable Module Size
40 MW
Fact
Full Potential Investment
€7.50 billion+
Fact
Phase 1 Construction Jobs
2,000 jobs approximately
Fact
Campus Job Impact
3,000 jobs+
Fact
Tenant Disclosed By Operator
False
Fact
Waste Heat Recovery Intended
True
Fact
Phase 1 Debt Is Full Campus Financing
False
Fact
Operating It Capacity Disclosed
False
Fact