Cartis diligence evidence schedule
Pure DC DUB01
PRJ-0508 · Site · Ballycoolin, Dublin 15, Ireland
Record last updated Oct 28, 2026
Scope and capacity
DUB01 is the live 14 MW first building at Pure DC's Ballycoolin campus and supports high-density workloads.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (1)
Project identity · Pure DC DUB01
Source report · Pure DC DUB01 (Project)
Claim 132364 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Dublin (Ballycoolin)
Pure Data Centres Group · Document date: Not stated · Primary
Source reference: SRC-6998 · Fact sheet · Recorded authority: Party primary
Source URL
https://puredc.com/dublin
https://puredc.com/dublin
- Ballycoolin environmental impact assessment record
Fingal County Council · Document date: Aug 31, 2026 · Primary
Source reference: SRC-7010 · Government record · Recorded authority: Official primary
Source URL
https://www.fingal.ie/council/service/planning-applications-environmental-impact-assessment-report
https://www.fingal.ie/council/service/planning-applications-environmental-impact-assessment-report
Counterparties and capital
Pure Data Centres Group · Operator · CMP-0741
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.