Project Zodiac - Phase 1

Fort Wayne, Indiana, United StatesOperating / Stabilized
Capacity
1,200 MW
Planned / design
Lead participant
Google
Developer
Last updated
Aug 29, 2026
Most recent public record update

About Project Zodiac - Phase 1

Google’s Fort Wayne, Indiana data center is an operating Google campus.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential1,200 MWDesign · Project Zodiac - Phase 1

Development

1 phases · 1 milestones
Operating campus; historical Phase 1 development identityOperational

Google’s Fort Wayne, Indiana data center is an operating Google campus.

Apr 19, 2024
Google confirmed it was the company behind Project Zodiac
Completed

Infrastructure

Electric GridOperational

1,200 MW

The 1.2 GW figure is not verified as operating IT load.

Project map

0 of 1 project point mapped
Infrastructure facts
1
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1

Facts & sources

Published claims and their source links.

8 facts
Location Context
Project Zodiac - Phase 1 | Fort Wayne | Indiana | US
Actual
Lifecycle Status
Operating
Actual
Reported Capacity
1,200 MW
Design
Capacity Basis
1,200 MW future full build site capacity; not measured operating IT load.
Actual
Operator Confirmed
Google
Actual
Operating Location
Fort Wayne, Indiana
Actual
Reported Investment
$2,000,000,000
Reported Rounded
Site Area
700 acres
Reported Rounded