Cartis diligence evidence schedule

Project Marvel

PRJ-1118 · Site · Bessemer, Alabama, United States

Record last updated Oct 28, 2026

Scope and capacity

QTS is developing a data center campus in Bessemer, Alabama. The project remains in public planning, and Bessemer revised the development framework after community feedback concerning nearby homes and the planned Northern Beltline.

Headline: 1,200 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Project Marvel | Bessemer | Alabama | US

Actual · Project Marvel (Project)

Claim 71794 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Project Marvel public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4098 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/alabama/

Lifecycle status · Proposed

Actual · Project Marvel (Project)

Claim 71795 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Project Marvel public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4098 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/alabama/

Reported capacity · 1,200 MW

Planned / design or future potential · Project Marvel (Project)

Claim 71796 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Project Marvel public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4098 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/alabama/

Capacity basis · 1,200 MW future full build site capacity; not measured operating IT load.

Actual · Project Marvel (Project)

Claim 71797 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Project Marvel public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4098 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/alabama/

Developer confirmed · QTS Data Centers

Actual · Project Marvel (Project)

Claim 77602 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. QTS Bessemer data center campus

    QTS Data Centers · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4385 · Company announcement · Recorded authority: Party primary

    Source URL

    https://q.com/datacenterlocation/alabama/

Planning framework · Revised after public feedback

Actual · Project Marvel (Project)

Claim 77603 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Updated development plans for proposed data center project

    City of Bessemer · Document date: Jan 20, 2026 · Primary

    Source reference: SRC-4386 · Government record · Recorded authority: Official primary

    Source URL

    https://bessemeral.org/?p=7329

Counterparties and capital

QTS Data Centers · Developer · CMP-0368

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.