Project Cardinal Data Center

Yorkville, Illinois, United StatesProposed
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Project Cardinal is Pioneer Development’s proposed data center campus in Yorkville, Illinois. City records cover roughly 1,037 acres, a planned-unit development and a campus concept with 14 buildings, including 11 large and three smaller facilities. The tracked 1.8 GW figure is not published as an approved operating or contracted capacity by the city, so Tertiary utility plans, transmission, water, sound controls, building permits, tenants and construction phases remain under review.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Approved master plan; utilities and building permits pendingAnnounced or preconstruction

14 buildings

Project Cardinal is Pioneer Development’s proposed data center campus in Yorkville, Illinois. City records cover roughly 1,037 acres, a planned-unit development and a campus concept with 14 buildings, including 11 large and three smaller facilities. The tracked 1.8 GW figure is not published as an approved operating or contracted capacity by the city, so the available public sources do not establish a single project-scoped capacity figure. Tertiary utility plans, transmission, water, sound controls, building permits, tenants and construction phases remain under review.

Milestones (1)
Planned-unit development approved

Nov 2025 · Recorded actual event

Completed · Permit approved

Source not linked

Participants

Pioneer Development

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

Project Cardinal Data Center | Yorkville | Illinois | US

Source

Location context

Actual

Project Cardinal Data Center | Yorkville | Illinois | US

Source

Site area

Actual

1,037 acres

Source

Building count

Actual

14 buildings

Source

Large buildings

Actual

11 buildings

Source

Small buildings

Actual

3 buildings

Source

Additional project facts

Lifecycle status

Actual

Proposed

Source

Capacity basis

Actual

1,800 MW future full build site capacity; not measured operating IT load.

Source

Lifecycle status

Actual

Proposed

Source

Infrastructure & permits

Technical details (1)
Utility service

Potential or planned

1,800 MW

Capacity estimate not verified in the city approval record.

Other · Issued

Project Cardinal

City of Yorkville

Nov 1, 2025

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.