Project Cannoli

Wayne, Michigan, United StatesProposed
Evidence
Planned / design
1,000 MW
Updated
Oct 28, 2026

On October 1, 2026, the Michigan Public Service Commission conditionally approved the DTE–Google utility contract, and Wayne County overrode the Project Cannoli incentives veto. Utility and incentive decisions are distinct from final site-plan approval and do not authorize or demonstrate campus construction or opening. Panattoni’s Project Cannoli is a proposed three-data center campus on roughly 282 acres in Van Buren Township, Michigan. The township granted preliminary site-plan approval with conditions in February 2026; the design includes support buildings, a substation, preserved open space and water and noise controls.

Capacity

Reported capacity

Planned / design or future potential

1,000 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Preliminary site-plan approvalAnnounced or preconstruction

Panattoni’s Project Cannoli is a proposed three-data center campus on roughly 282 acres in Van Buren Township, Michigan. The township granted preliminary site-plan approval with conditions in February 2026; the design includes support buildings, a substation, preserved open space and water and noise controls.

Milestones (1)
Planning Commission considered and granted conditional preliminary approval

Feb 11, 2026 · Recorded actual event

Completed · Permit approved

Source not linked

Participants

Panattoni Development Company

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

Project Cannoli | Wayne | Michigan | US

Source

Site area

Actual

282.2 acres

Source

Data center buildings

Actual

3 buildings

Source

Support buildings

Actual

2 buildings

Source

Construction jobs

Reported rounded

1,500 jobs

Source

Additional project facts

Lifecycle status

Actual

Proposed

Source

Capacity basis

Actual

1,000 MW future full build site capacity; not measured operating IT load.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

Transmission-level power and customer-funded infrastructure.

Water

Planned or represented

No groundwater; GLWA supply and no discharge to Belleville Lake or ground.

Other · Issued

Project Cannoli

Van Buren Township

Feb 11, 2026

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.