Prime PHX01 Avondale Campus
PRJ-0037 · Site · 3700–3716 S. Avondale Boulevard, Avondale, Arizona, United States
Captured 2026-09-06T04:13:04.440Z · Record last updated 2026-08-22
SHA-256: b1dad5ced235448e9438ca9dfd4ed912ba6df26923f8f3b6d4ee06b93aed186d
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
Prime has begun the first three facilities at its five-building PHX01 campus in Avondale. The campus is designed for 240 MW of critical IT capacity, but no operating IT load is yet evidenced.
Headline: 240 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Project Status · Under construction
actual · Prime PHX01 Avondale Campus (project)
Claim 5255 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
- Prime Data Centers breaks ground on three out of five buildings at its 240MW campus in Phoenix, Arizona
Data Center Dynamics · Document date: 2026-05-22 · Corroborating
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/ - Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/ - Phoenix Campus PHX01
Prime Data Centers · Document date: Not published · Corroborating
https://primedatacenters.com/locations/phoenix/
Full Campus Critical It Capacity · 240 MW
forecast · Prime PHX01 Avondale Campus (project)
Claim 5256 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00 · Supersedes 5254
Headline treatment: Selected headline
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/ - Phoenix Campus PHX01
Prime Data Centers · Document date: Not published · Corroborating
https://primedatacenters.com/locations/phoenix/
Site Area · 66.5 acres
actual · Prime PHX01 Avondale Campus (project)
Claim 5257 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/ - Phoenix Campus PHX01
Prime Data Centers · Document date: Not published · Corroborating
https://primedatacenters.com/locations/phoenix/
Planned Floor Area · 1,300,000 sq. ft.
Planned / design or future potential · Prime PHX01 Avondale Campus (project)
Claim 5258 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/ - Phoenix Campus PHX01
Prime Data Centers · Document date: Not published · Corroborating
https://primedatacenters.com/locations/phoenix/
Planned Data Center Buildings · 5 count
Planned / design or future potential · Prime PHX01 Avondale Campus (project)
Claim 5259 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/ - Phoenix Campus PHX01
Prime Data Centers · Document date: Not published · Corroborating
https://primedatacenters.com/locations/phoenix/
Planned Data Halls · 20 count
Planned / design or future potential · Prime PHX01 Avondale Campus (project)
Claim 5260 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/ - Phoenix Campus PHX01
Prime Data Centers · Document date: Not published · Corroborating
https://primedatacenters.com/locations/phoenix/
Announced Investment · $>3000000000
transaction scope · Prime PHX01 Avondale Campus (project)
Claim 5261 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/ - $3 Billion Avondale Data Center Breaks Ground
Greater Phoenix Economic Council · Document date: 2026-05-21 · Corroborating
https://metrophoenix.com/2026/05/3-billion-avondale-data-center-breaks-ground/
Groundbreaking Date · 2026-05-21
actual · Opening construction phase — PHX01-01 to PHX01-03 (phase)
Claim 5262 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
- Prime Data Centers breaks ground on three out of five buildings at its 240MW campus in Phoenix, Arizona
Data Center Dynamics · Document date: 2026-05-22 · Corroborating
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/ - Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/ - $3 Billion Avondale Data Center Breaks Ground
Greater Phoenix Economic Council · Document date: 2026-05-21 · Corroborating
https://metrophoenix.com/2026/05/3-billion-avondale-data-center-breaks-ground/
Building Count · 3 count
actual · Opening construction phase — PHX01-01 to PHX01-03 (phase)
Claim 5263 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
- Prime Data Centers breaks ground on three out of five buildings at its 240MW campus in Phoenix, Arizona
Data Center Dynamics · Document date: 2026-05-22 · Corroborating
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/ - Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
Per Building Critical It Design · 48 MW
design · Opening construction phase — PHX01-01 to PHX01-03 (phase)
Claim 5264 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
Headline treatment: Phase scope; not a whole-site figure
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/ - Phoenix Campus PHX01
Prime Data Centers · Document date: Not published · Corroborating
https://primedatacenters.com/locations/phoenix/
Opening Phase Critical It Design · 144 MW
design · Opening construction phase — PHX01-01 to PHX01-03 (phase)
Claim 5265 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
Headline treatment: Phase scope; not a whole-site figure
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
Customer Status · Secured by one undisclosed leading hyperscaler
transaction scope · Opening construction phase — PHX01-01 to PHX01-03 (phase)
Claim 5266 · Review: Approved · Claim date: 2026-05-21T00:00:00+00:00
- Prime Data Centers breaks ground on three out of five buildings at its 240MW campus in Phoenix, Arizona
Data Center Dynamics · Document date: 2026-05-22 · Corroborating
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/ - Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: 2026-05-21 · Primary
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
Current Operator Status · Construction
actual · PHX01-04 (phase)
Claim 5267 · Review: Approved · Claim date: Not published
Conflicting public evidence is preserved.
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not published · Primary
https://primedatacenters.com/locations/phoenix/
Current Operator Status · Development
actual · PHX01-05 (phase)
Claim 5268 · Review: Approved · Claim date: Not published
Conflicting public evidence is preserved.
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not published · Primary
https://primedatacenters.com/locations/phoenix/
Counterparties and capital
ARCO/Murray · Contractor · CMP-0170
City of Avondale · Government Authority · CMP-0168
Prime Data Centers · Operator · CMP-0167
Salt River Project · Utility Provider · CMP-0169
Undisclosed leading hyperscaler · Customer · CMP-0171
$3,000,000,000 · 2026-05-21
More-than amount for Prime's campus investment; no debt/equity close or customer spend allocation recorded.
Prime Data Centers (Sponsor)
Financing record 31; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.