Cartis diligence evidence schedule
Prime PHX01 Avondale Campus
PRJ-0037 · Site · 3700–3716 S. Avondale Boulevard, Avondale, Arizona, United States
Record last updated Oct 28, 2026
Scope and capacity
Prime has begun the first three facilities at its five-building PHX01 campus in Avondale. The campus is designed for 240 MW of critical IT capacity, but no operating IT load is yet evidenced.
Headline: 240 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (14)
Project status · Under construction
Actual · Prime PHX01 Avondale Campus (Project)
Claim 5255 · Recorded claim type: Actual · Review: Approved · Claim date: May 21, 2026
- Prime Data Centers breaks ground on three out of five buildings at its 240MW campus in Phoenix, Arizona
Data Center Dynamics · Document date: May 22, 2026 · Corroborating
Source reference: SRC-0288 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not stated · Corroborating
Source reference: SRC-0286 · Fact sheet · Recorded authority: Party primary
Source URL
https://primedatacenters.com/locations/phoenix/
https://primedatacenters.com/locations/phoenix/
Full campus critical IT capacity · 240 MW
Forecast · Prime PHX01 Avondale Campus (Project)
Claim 5256 · Recorded claim type: Forecast · Review: Approved · Claim date: May 21, 2026
Headline treatment: Selected headline
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not stated · Corroborating
Source reference: SRC-0286 · Fact sheet · Recorded authority: Party primary
Source URL
https://primedatacenters.com/locations/phoenix/
https://primedatacenters.com/locations/phoenix/
Site area · 66.5 acres
Actual · Prime PHX01 Avondale Campus (Project)
Claim 5257 · Recorded claim type: Actual · Review: Approved · Claim date: May 21, 2026
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not stated · Corroborating
Source reference: SRC-0286 · Fact sheet · Recorded authority: Party primary
Source URL
https://primedatacenters.com/locations/phoenix/
https://primedatacenters.com/locations/phoenix/
Planned floor area · 1,300,000 sq. ft.
Forecast · Prime PHX01 Avondale Campus (Project)
Claim 5258 · Recorded claim type: Forecast · Review: Approved · Claim date: May 21, 2026
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not stated · Corroborating
Source reference: SRC-0286 · Fact sheet · Recorded authority: Party primary
Source URL
https://primedatacenters.com/locations/phoenix/
https://primedatacenters.com/locations/phoenix/
Planned data center buildings · 5 count
Forecast · Prime PHX01 Avondale Campus (Project)
Claim 5259 · Recorded claim type: Forecast · Review: Approved · Claim date: May 21, 2026
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not stated · Corroborating
Source reference: SRC-0286 · Fact sheet · Recorded authority: Party primary
Source URL
https://primedatacenters.com/locations/phoenix/
https://primedatacenters.com/locations/phoenix/
Planned data halls · 20 count
Forecast · Prime PHX01 Avondale Campus (Project)
Claim 5260 · Recorded claim type: Forecast · Review: Approved · Claim date: May 21, 2026
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not stated · Corroborating
Source reference: SRC-0286 · Fact sheet · Recorded authority: Party primary
Source URL
https://primedatacenters.com/locations/phoenix/
https://primedatacenters.com/locations/phoenix/
Announced investment · $>3000000000
Transaction scope · Prime PHX01 Avondale Campus (Project)
Claim 5261 · Recorded claim type: Transaction scope · Review: Approved · Claim date: May 21, 2026
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
- $3 Billion Avondale Data Center Breaks Ground
Greater Phoenix Economic Council · Document date: May 21, 2026 · Corroborating
Source reference: SRC-0289 · News report · Recorded authority: Official primary
Source URL
https://metrophoenix.com/2026/05/3-billion-avondale-data-center-breaks-ground/
https://metrophoenix.com/2026/05/3-billion-avondale-data-center-breaks-ground/
Groundbreaking date · 2026-05-21
Actual · Opening construction phase — PHX01-01 to PHX01-03 (Phase)
Claim 5262 · Recorded claim type: Actual · Review: Approved · Claim date: May 21, 2026
- Prime Data Centers breaks ground on three out of five buildings at its 240MW campus in Phoenix, Arizona
Data Center Dynamics · Document date: May 22, 2026 · Corroborating
Source reference: SRC-0288 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
- $3 Billion Avondale Data Center Breaks Ground
Greater Phoenix Economic Council · Document date: May 21, 2026 · Corroborating
Source reference: SRC-0289 · News report · Recorded authority: Official primary
Source URL
https://metrophoenix.com/2026/05/3-billion-avondale-data-center-breaks-ground/
https://metrophoenix.com/2026/05/3-billion-avondale-data-center-breaks-ground/
Building count · 3 count
Actual · Opening construction phase — PHX01-01 to PHX01-03 (Phase)
Claim 5263 · Recorded claim type: Actual · Review: Approved · Claim date: May 21, 2026
- Prime Data Centers breaks ground on three out of five buildings at its 240MW campus in Phoenix, Arizona
Data Center Dynamics · Document date: May 22, 2026 · Corroborating
Source reference: SRC-0288 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
Per building critical IT design · 48 MW
Design · Opening construction phase — PHX01-01 to PHX01-03 (Phase)
Claim 5264 · Recorded claim type: Design · Review: Approved · Claim date: May 21, 2026
Headline treatment: Phase scope; not a whole-site figure
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not stated · Corroborating
Source reference: SRC-0286 · Fact sheet · Recorded authority: Party primary
Source URL
https://primedatacenters.com/locations/phoenix/
https://primedatacenters.com/locations/phoenix/
Opening phase critical IT design · 144 MW
Design · Opening construction phase — PHX01-01 to PHX01-03 (Phase)
Claim 5265 · Recorded claim type: Design · Review: Approved · Claim date: May 21, 2026
Headline treatment: Phase scope; not a whole-site figure
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
Customer status · Secured by one undisclosed leading hyperscaler
Transaction scope · Opening construction phase — PHX01-01 to PHX01-03 (Phase)
Claim 5266 · Recorded claim type: Transaction scope · Review: Approved · Claim date: May 21, 2026
- Prime Data Centers breaks ground on three out of five buildings at its 240MW campus in Phoenix, Arizona
Data Center Dynamics · Document date: May 22, 2026 · Corroborating
Source reference: SRC-0288 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/
https://www.datacenterdynamics.com/en/news/prime-data-centers-breaks-ground-on-three-out-of-five-buildings-at-its-240mw-campus-in-phoenix-arizona/
- Prime Data Centers Breaks Ground on Three Buildings at its 240MW Campus in Phoenix, Advancing $3B Investment in Avondale
Prime Data Centers · Document date: May 21, 2026 · Primary
Source reference: SRC-0285 · Company announcement · Recorded authority: Party primary
Source URL
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
https://primedatacenters.com/news/prime-data-centers-breaks-ground-on-three-buildings-at-its-240mw-phoenix-campus-advancing-3billion-dollar-investment-in-avondale/
Current operator status · Construction
Actual · PHX01-04 (Phase)
Claim 5267 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Conflicting public evidence is preserved.
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not stated · Primary
Source reference: SRC-0286 · Fact sheet · Recorded authority: Party primary
Source URL
https://primedatacenters.com/locations/phoenix/
https://primedatacenters.com/locations/phoenix/
Current operator status · Development
Actual · PHX01-05 (Phase)
Claim 5268 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Conflicting public evidence is preserved.
- Phoenix Campus PHX01
Prime Data Centers · Document date: Not stated · Primary
Source reference: SRC-0286 · Fact sheet · Recorded authority: Party primary
Source URL
https://primedatacenters.com/locations/phoenix/
https://primedatacenters.com/locations/phoenix/
Counterparties and capital
ARCO/Murray · Contractor · CMP-0170
City of Avondale · Government authority · CMP-0168
Prime Data Centers · Operator · CMP-0167
Salt River Project · Utility provider · CMP-0169
Undisclosed leading hyperscaler · Customer · CMP-0171
$3,000,000,000 · May 21, 2026
More-than amount for Prime's campus investment; no debt/equity close or customer spend allocation recorded.
Prime Data Centers (Sponsor)
Financing record 31; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.