Skip to content
← Return to profile

Cartis diligence evidence schedule

Prime Madrid MAD01 Data Center Campus

PRJ-0805 · Site · Alcobendas, Community of Madrid, Spain

Captured 2026-09-06T04:13:13.739Z · Record last updated 2026-08-28

SHA-256: 3bd6ccb4051c8253dcd2771132dbed32776927aab746178da8f97c62a29b2a47

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Prime Madrid MAD01 Data Center Campus, also known as Prime Madrid MAD01, is a data center project in Alcobendas, Community of Madrid, ES associated with Prime Data Centers. Eight-acre site; one planned hyperscale building; 25,810 square metres; 40 MW critical IT load. On-site-substation Madrid campus with closed-loop air and liquid cooling and ten carriers on campus. 40 MW is the source-defined future IT or site design envelope. Disclosed investment or financing context is recorded with its transaction scope and is not treated as delivered project cost or proof of capacity.

Headline: 40 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Location Context · Prime Madrid MAD01 | Alcobendas | Community of Madrid | ES

actual · Prime Madrid MAD01 Data Center Campus (project)

Claim 61092 · Review: Approved · Claim date: Not published

  1. Prime Data Centers Prime Madrid MAD01 profile

    Prime Data Centers · Document date: 2026-08-27 · Primary

    https://primedatacenters.com/locations/madrid/

Lifecycle Status · Preconstruction

actual · Prime Madrid MAD01 Data Center Campus (project)

Claim 61093 · Review: Approved · Claim date: Not published

  1. Prime Data Centers Prime Madrid MAD01 profile

    Prime Data Centers · Document date: 2026-08-27 · Primary

    https://primedatacenters.com/locations/madrid/

Reported Capacity · 40 MW

design · Prime Madrid MAD01 Data Center Campus (project)

Claim 61094 · Review: Approved · Claim date: Not published

Headline treatment: Separate claim, not added to the headline

  1. Prime Data Centers Prime Madrid MAD01 profile

    Prime Data Centers · Document date: 2026-08-27 · Primary

    https://primedatacenters.com/locations/madrid/

Capacity Basis · Prime Data Centers publishes 40 MW of critical IT capacity for this record boundary.

actual · Prime Madrid MAD01 Data Center Campus (project)

Claim 61095 · Review: Approved · Claim date: Not published

  1. Prime Data Centers Prime Madrid MAD01 profile

    Prime Data Centers · Document date: 2026-08-27 · Primary

    https://primedatacenters.com/locations/madrid/

Location Context · Prime Madrid MAD01 | Alcobendas | Community of Madrid | ES

actual · Prime Madrid MAD01 Data Center Campus (project)

Claim 101101 · Review: Approved · Claim date: Not published

  1. Prime Data Centers Prime Madrid MAD01 profile

    Prime Data Centers · Document date: 2026-08-27 · Primary

    https://primedatacenters.com/locations/madrid/

Lifecycle Status · Preconstruction

actual · Prime Madrid MAD01 Data Center Campus (project)

Claim 101102 · Review: Approved · Claim date: Not published

  1. Prime Data Centers Prime Madrid MAD01 profile

    Prime Data Centers · Document date: 2026-08-27 · Primary

    https://primedatacenters.com/locations/madrid/

Reported Capacity · 40 MW

Planned / design or future potential · Prime Madrid MAD01 Data Center Campus (project)

Claim 101103 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. Prime Data Centers Prime Madrid MAD01 profile

    Prime Data Centers · Document date: 2026-08-27 · Primary

    https://primedatacenters.com/locations/madrid/

Capacity Basis · 40 MW is the source defined future IT or site design envelope.

Planned / design or future potential · Prime Madrid MAD01 Data Center Campus (project)

Claim 101104 · Review: Approved · Claim date: Not published

  1. Prime Data Centers Prime Madrid MAD01 profile

    Prime Data Centers · Document date: 2026-08-27 · Primary

    https://primedatacenters.com/locations/madrid/

Project Identity · Prime Madrid MAD01

actual · Prime Madrid MAD01 Data Center Campus (project)

Claim 101106 · Review: Approved · Claim date: Not published

  1. Prime announces MAD01

    Prime Data Centers · Document date: 2024-05-21 · Primary

    https://primedatacenters.com/news/prime-madrid-data-center/

Location Context · Alcobendas, Community of Madrid, ES

actual · Prime Madrid MAD01 Data Center Campus (project)

Claim 101107 · Review: Approved · Claim date: Not published

  1. Prime announces MAD01

    Prime Data Centers · Document date: 2024-05-21 · Primary

    https://primedatacenters.com/news/prime-madrid-data-center/

Lifecycle Status · Preconstruction

actual · Prime Madrid MAD01 Data Center Campus (project)

Claim 101108 · Review: Approved · Claim date: Not published

  1. Prime announces MAD01

    Prime Data Centers · Document date: 2024-05-21 · Primary

    https://primedatacenters.com/news/prime-madrid-data-center/

Development Detail · Eight acre site; one planned hyperscale building; 25,810 square metres; 40 MW critical IT load.

Planned / design or future potential · Prime Madrid MAD01 Data Center Campus (project)

Claim 101109 · Review: Approved · Claim date: Not published

  1. Prime announces MAD01

    Prime Data Centers · Document date: 2024-05-21 · Primary

    https://primedatacenters.com/news/prime-madrid-data-center/

Capacity Basis · 40 MW is the source defined future IT or site design envelope.

Planned / design or future potential · Prime Madrid MAD01 Data Center Campus (project)

Claim 101110 · Review: Approved · Claim date: Not published

  1. Prime announces MAD01

    Prime Data Centers · Document date: 2024-05-21 · Primary

    https://primedatacenters.com/news/prime-madrid-data-center/

Counterparties and capital

Iberdrola · Utility Provider · CMP-1620

Prime Data Centers · Developer · CMP-0167

Equity Investment

Amount not disclosed · 2025-10-14

Platform-level funding context; no site-level amount is inferred.

Prime Data Centers (Borrower)

Financing record 198; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.