Scope and capacity
The PORTS operator's current FAQ, checked October 28, 2026, reports that early civil works have begun and forecasts first-phase capacity coming online in stages beginning in 2028. These early works and forecasts concern the first 800 MW phase, not delivery of the entire planned 10 GW campus. Planned compute campus across DOE and nearby private land. Power generation, transmission and DOE lease remain separately typed. PORTS Technology Campus is located in Piketon, OH, US and is a data center campus in early site-development status.
Headline: 10,000 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (11)
Planned campus design capacity · 10 GW
Planned / design or future potential · PORTS Technology Campus (Project)
Claim 33794 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- PORTS Technology Campus latest to gain FAST-41 coverage
Federal Permitting Improvement Steering Council · Document date: Jun 16, 2026 · Corroborating
Source reference: SRC-1888 · Government record · Recorded authority: Official primary
Source URL
https://www.permitting.gov/newsroom/press-releases/ports-technology-campus-latest-gain-fast-41-coverage
https://www.permitting.gov/newsroom/press-releases/ports-technology-campus-latest-gain-fast-41-coverage
- Energy Department announces partnership to ensure affordable energy and power America's AI
U.S. Department of Energy · Document date: Mar 20, 2026 · Primary
Source reference: SRC-1884 · Government record · Recorded authority: Official primary
Source URL
https://www.energy.gov/articles/energy-department-announces-partnership-ensure-affordable-energy-and-power-americas-ai
https://www.energy.gov/articles/energy-department-announces-partnership-ensure-affordable-energy-and-power-americas-ai
- PORTS Technology Campus
PORTS Technology Campus · Document date: Mar 20, 2026 · Corroborating
Source reference: SRC-1887 · Company announcement · Recorded authority: Party primary
Source URL
https://portscampus.com/
https://portscampus.com/
Planned first phase capacity · 800 MW
Planned / design or future potential · PORTS Technology Campus (Project)
Claim 33795 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- PORTS Technology Campus
PORTS Technology Campus · Document date: Mar 20, 2026 · Primary
Source reference: SRC-1887 · Company announcement · Recorded authority: Party primary
Source URL
https://portscampus.com/
https://portscampus.com/
First phase construction target year · 2026
Actual · PORTS Technology Campus (Project)
Claim 33796 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Partnership ensures affordable energy, powers AI future at Portsmouth Site
U.S. Department of Energy · Document date: Mar 24, 2026 · Corroborating
Source reference: SRC-1885 · Government record · Recorded authority: Official primary
Source URL
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
- PORTS Technology Campus
PORTS Technology Campus · Document date: Mar 20, 2026 · Primary
Source reference: SRC-1887 · Company announcement · Recorded authority: Party primary
Source URL
https://portscampus.com/
https://portscampus.com/
Initial federal lease area · 189 acres
Actual · PORTS Technology Campus (Project)
Claim 33797 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Partnership ensures affordable energy, powers AI future at Portsmouth Site
U.S. Department of Energy · Document date: Mar 24, 2026 · Primary
Source reference: SRC-1885 · Government record · Recorded authority: Official primary
Source URL
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
Federal and private land components · True
Actual · PORTS Technology Campus (Project)
Claim 33798 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- PORTS Technology Campus: 10GW AI data center in Piketon, Ohio
Aterio · Document date: Jul 27, 2026 · Corroborating
Source reference: SRC-1892 · Recorded authority: Secondary
Source URL
https://www.aterio.io/blog/ports-technology-campus-sb-energy-10gw-ai-data-center-piketon-ohio
https://www.aterio.io/blog/ports-technology-campus-sb-energy-10gw-ai-data-center-piketon-ohio
- PORTS Technology Campus latest to gain FAST-41 coverage
Federal Permitting Improvement Steering Council · Document date: Jun 16, 2026 · Primary
Source reference: SRC-1888 · Government record · Recorded authority: Official primary
Source URL
https://www.permitting.gov/newsroom/press-releases/ports-technology-campus-latest-gain-fast-41-coverage
https://www.permitting.gov/newsroom/press-releases/ports-technology-campus-latest-gain-fast-41-coverage
Ceremonial groundbreaking held · True
Actual · PORTS Technology Campus (Project)
Claim 33799 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Partnership ensures affordable energy, powers AI future at Portsmouth Site
U.S. Department of Energy · Document date: Mar 24, 2026 · Primary
Source reference: SRC-1885 · Government record · Recorded authority: Official primary
Source URL
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
- PORTS Technology Campus groundbreaking webcast
SoftBank Group · Document date: Mar 21, 2026 · Corroborating
Source reference: SRC-1893 · Recorded authority: Party primary
Source URL
https://group.softbank/en/news/info/20260321
https://group.softbank/en/news/info/20260321
Fast 41 covered project · True
Actual · PORTS Technology Campus (Project)
Claim 33801 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- PORTS Technology Campus latest to gain FAST-41 coverage
Federal Permitting Improvement Steering Council · Document date: Jun 16, 2026 · Primary
Source reference: SRC-1888 · Government record · Recorded authority: Official primary
Source URL
https://www.permitting.gov/newsroom/press-releases/ports-technology-campus-latest-gain-fast-41-coverage
https://www.permitting.gov/newsroom/press-releases/ports-technology-campus-latest-gain-fast-41-coverage
Sponsor reported construction jobs · 35,000 jobs
Actual · PORTS Technology Campus (Project)
Claim 33804 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Conflicting public evidence is preserved.
- PORTS Technology Campus
PORTS Technology Campus · Document date: Mar 20, 2026 · Primary
Source reference: SRC-1887 · Company announcement · Recorded authority: Party primary
Source URL
https://portscampus.com/
https://portscampus.com/
Government reported construction jobs · 10,000 jobs
Actual · PORTS Technology Campus (Project)
Claim 33805 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Conflicting public evidence is preserved.
- Partnership ensures affordable energy, powers AI future at Portsmouth Site
U.S. Department of Energy · Document date: Mar 24, 2026 · Primary
Source reference: SRC-1885 · Government record · Recorded authority: Official primary
Source URL
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
Sponsor reported operating jobs · 2,500 jobs
Actual · PORTS Technology Campus (Project)
Claim 33806 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- PORTS Technology Campus
PORTS Technology Campus · Document date: Mar 20, 2026 · Primary
Source reference: SRC-1887 · Company announcement · Recorded authority: Party primary
Source URL
https://portscampus.com/
https://portscampus.com/
Government reported permanent jobs greater than · 2,000 jobs
Actual · PORTS Technology Campus (Project)
Claim 33807 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Partnership ensures affordable energy, powers AI future at Portsmouth Site
U.S. Department of Energy · Document date: Mar 24, 2026 · Primary
Source reference: SRC-1885 · Government record · Recorded authority: Official primary
Source URL
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
https://www.energy.gov/em/articles/partnership-ensures-affordable-energy-powers-ai-future-portsmouth-site
Counterparties and capital
SB Energy · Developer · CMP-0908
U.S. Army Corps of Engineers · Government authority · CMP-0909
U.S. Department of Energy · Government authority · CMP-0675
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.