Peru Shelf Technology Park

Sparks, Nevada, United StatesPreconstruction
Capacity
810 MW
Planned / design
Lead participant
Tract
Developer
Last updated
Aug 28, 2026
Most recent public record update

About Peru Shelf Technology Park

Tract’s Peru Shelf Technology Park is an 810 MW, 686-acre powered-land development within the Tahoe-Reno Industrial Center. Horizontal construction began in April 2024 and includes access roads, wet utilities and switch-station grading, with site energization targeted for February 2027.

Projects sharing a market, utility, or organization.

2 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential810 MWDesign · Peru Shelf Technology Park

Development

1 phases · 2 milestones
Horizontal constructionUnder Construction

Tract’s Peru Shelf Technology Park is an 810 MW, 686-acre powered-land development within the Tahoe-Reno Industrial Center. Horizontal construction began in April 2024 and includes access roads, wet utilities and switch-station grading, with site energization targeted for February 2027.

Apr 30, 2024
Horizontal development groundbreaking
Completed
Feb 1, 2027
Target site energization
Forecast

Infrastructure

Electric GridUnder Construction

810 MW

NV Energy switch stations, access and wet utilities included in horizontal development.

Project map

0 of 1 project point mapped
Infrastructure facts
1
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1

Facts & sources

Published claims and their source links.

7 facts
Location Context
Peru Shelf Technology Park | Sparks | Nevada | US
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
810 MW
Design
Capacity Basis
810 MW future full build site capacity; not measured operating IT load.
Actual
Site Area
686 acres
Actual
Parcel Size Range
183–277 Acres
Actual
Target Energization
February 2027
Actual