Scope and capacity
PDG MU2 Navi Mumbai is one approximately 10-acre, five-story physical facility. It is separate from MU1's five-building Airoli campus and from PDG's 210 MW India acquisition and 1 GW country portfolio.
Headline: 120 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (13)
Site area · 10 acres approximate
Source report · PDG MU2 Navi Mumbai (Project)
Claim 45899 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- PDG breaks ground on latest Mumbai data center
Data Center Dynamics · Document date: Apr 10, 2026 · Primary
Source reference: SRC-2528
Source URL
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
- PDG India Data Centers — MU2 Facility
Princeton Digital Group · Document date: Not stated · Primary
Source reference: SRC-2527
Source URL
https://princetondg.com/locations/india/
https://princetondg.com/locations/india/
Building count · 1 facility
Source report · PDG MU2 Navi Mumbai (Project)
Claim 45900 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- PDG breaks ground on latest Mumbai data center
Data Center Dynamics · Document date: Apr 10, 2026 · Primary
Source reference: SRC-2528
Source URL
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
- PDG India Data Centers — MU2 Facility
Princeton Digital Group · Document date: Not stated · Primary
Source reference: SRC-2527
Source URL
https://princetondg.com/locations/india/
https://princetondg.com/locations/india/
Building storeys · 5 storeys
Source report · PDG MU2 Navi Mumbai (Project)
Claim 45901 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- PDG breaks ground on latest Mumbai data center
Data Center Dynamics · Document date: Apr 10, 2026 · Primary
Source reference: SRC-2528
Source URL
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
- PDG India Data Centers — MU2 Facility
Princeton Digital Group · Document date: Not stated · Primary
Source reference: SRC-2527
Source URL
https://princetondg.com/locations/india/
https://princetondg.com/locations/india/
Critical IT design capacity · 120 MW
Planned / design or future potential · PDG MU2 Navi Mumbai (Project)
Claim 45902 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- PDG breaks ground on latest Mumbai data center
Data Center Dynamics · Document date: Apr 10, 2026 · Primary
Source reference: SRC-2528
Source URL
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
- PDG India Data Centers — MU2 Facility
Princeton Digital Group · Document date: Not stated · Primary
Source reference: SRC-2527
Source URL
https://princetondg.com/locations/india/
https://princetondg.com/locations/india/
Colocation area · 18,880 square metres
Source report · PDG MU2 Navi Mumbai (Project)
Claim 45903 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- PDG India Data Centers — MU2 Facility
Princeton Digital Group · Document date: Not stated · Primary
Source reference: SRC-2527
Source URL
https://princetondg.com/locations/india/
https://princetondg.com/locations/india/
Network model · Carrier neutral
Actual · PDG MU2 Navi Mumbai (Project)
Claim 45904 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- PDG India Data Centers — MU2 Facility
Princeton Digital Group · Document date: Not stated · Primary
Source reference: SRC-2527
Source URL
https://princetondg.com/locations/india/
https://princetondg.com/locations/india/
Location · Navi Mumbai region
Actual · PDG MU2 Navi Mumbai (Project)
Claim 45905 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- PDG India Data Centers — MU2 Facility
Princeton Digital Group · Document date: Not stated · Primary
Source reference: SRC-2527
Source URL
https://princetondg.com/locations/india/
https://princetondg.com/locations/india/
Land acquired · 2026-03
Actual · PDG MU2 Navi Mumbai (Project)
Claim 45906 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- PDG breaks ground on latest Mumbai data center
Data Center Dynamics · Document date: Apr 10, 2026 · Primary
Source reference: SRC-2528
Source URL
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
Construction started · 2026-04
Actual · PDG MU2 Navi Mumbai (Project)
Claim 45907 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- PDG breaks ground on latest Mumbai data center
Data Center Dynamics · Document date: Apr 10, 2026 · Primary
Source reference: SRC-2528
Source URL
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
https://www.datacenterdynamics.com/en/news/pdg-breaks-ground-on-latest-mumbai-data-center/
Power secured · True
Source report · PDG MU2 Navi Mumbai (Project)
Claim 45911 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- PDG Acquires 210 MW in India, Advancing Toward a 1 GW Portfolio in the Country
Princeton Digital Group · Document date: Mar 24, 2026 · Primary
Source reference: SRC-2526
Source URL
https://princetondg.com/newsroom/pdg-acquires-210-mw-in-india-advancing-toward-a-1-gw-portfolio-in-the-country/
https://princetondg.com/newsroom/pdg-acquires-210-mw-in-india-advancing-toward-a-1-gw-portfolio-in-the-country/
Key land approvals in place · True
Source report · PDG MU2 Navi Mumbai (Project)
Claim 45912 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- PDG Acquires 210 MW in India, Advancing Toward a 1 GW Portfolio in the Country
Princeton Digital Group · Document date: Mar 24, 2026 · Primary
Source reference: SRC-2526
Source URL
https://princetondg.com/newsroom/pdg-acquires-210-mw-in-india-advancing-toward-a-1-gw-portfolio-in-the-country/
https://princetondg.com/newsroom/pdg-acquires-210-mw-in-india-advancing-toward-a-1-gw-portfolio-in-the-country/
Mu1 green financing applies · False
Source report · PDG MU2 Navi Mumbai (Project)
Claim 45913 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- PDG Secures ~USD 160 Million Green Loan for Mumbai Data Center Campus
Princeton Digital Group · Document date: Jul 30, 2025 · Primary
Source reference: SRC-2531
Source URL
https://princetondg.com/newsroom/princeton-digital-group-secures-usd-160-million-green-loan-for-mumbai-data-center-campus/
https://princetondg.com/newsroom/princeton-digital-group-secures-usd-160-million-green-loan-for-mumbai-data-center-campus/
Mu1 time matched cfe program applies · False
Source report · PDG MU2 Navi Mumbai (Project)
Claim 45914 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- PDG partners on time-matched carbon-free energy at Mumbai data center campus
Princeton Digital Group · Document date: Sep 18, 2025 · Primary
Source reference: SRC-2532
Source URL
https://princetondg.com/newsroom/princeton-digital-group-partners-with-flexidao-and-tata-power-renewables-to-pioneer-time-matched-carbon-free-energy-at-mumbai-data-center-campus/
https://princetondg.com/newsroom/princeton-digital-group-partners-with-flexidao-and-tata-power-renewables-to-pioneer-time-matched-carbon-free-energy-at-mumbai-data-center-campus/
Counterparties and capital
Mubadala Investment Company · Investor · CMP-1175
Ontario Teachers' Pension Plan · Investor · CMP-1174
Princeton Digital Group · Operator · CMP-1172
Stonepeak · Investor · CMP-1176
Warburg Pincus · Investor · CMP-1173
$750,000,000 · Mar 11, 2026
Closed PDG regional platform facility; no MU2 allocation. Separate from the planned up-to-USD5bn debt raise.
Deutsche Bank (Lending consortium member) · Princeton Digital Group (Borrower / financed platform)
Sources (1)
- PDG Targets USD 5 Billion Debt Raise · Mar 11, 2026
Financing record 137; claim-specific source links appear in the exhibit sources where published.