Cartis diligence evidence schedule

Paducah American Energy Hub

PRJ-PADUCAH-AEH · Site · U.S. Department of Energy Paducah Site, McCracken County, Kentucky, United States

Captured 2026-09-06T04:13:42.732Z · Record last updated 2026-07-29

SHA-256: a2432c2a0dc26bfe1f655da8c1deda4c636afc3a44c31225a07255b1181e017b

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Brookfield and NextEra were selected to negotiate a privately funded AI campus at DOE's Paducah site. The proposal targets more than 1.2 GW of compute, 1.8 GW of utility capacity, up to 2 GW of gas generation and 2.6 GW of battery storage, with full buildout by 2032.

Headline: 1,200 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Program Investment Plan · $100,000,000,000

brookfield ai infrastructure program context · Paducah American Energy Hub (project)

Claim AST-B2-047 · Review: Approved · Claim date: 2026-07-29

  1. DOE Paducah Site revitalized with data center and dedicated energy

    Brookfield Asset Management · Document date: 2026-07-29 · Supports

    https://bam.brookfield.com/press-releases/doe-site-western-kentucky-revitalized-data-center-campus-and-dedicated-energy

Utility Capacity · 1.8 GW

planned · Paducah American Energy Hub (project)

Claim AST-B2-048 · Review: Approved · Claim date: 2026-07-29

Headline treatment: Separate claim, not added to the headline

  1. DOE Paducah Site revitalized with data center campus

    NextEra Energy · Document date: 2026-07-29 · Supports

    https://www.investor.nexteraenergy.com/news-and-events/news-releases/2026/07-29-2026-133109921

Compute Capacity · 1.2+ GW

planned · Paducah American Energy Hub (project)

Claim AST-B2-049 · Review: Approved · Claim date: 2026-07-29

  1. NextEra and Brookfield plan $100 billion Kentucky data center

    Reuters · Document date: 2026-07-29 · Supports

    https://www.reuters.com/business/energy/brookfield-nextera-develop-100-billion-data-center-campus-kentucky-source-says-2026-07-29/

Natural Gas Generation · Up to 2 GW

planned · Paducah American Energy Hub (project)

Claim AST-B2-050 · Review: Approved · Claim date: 2026-07-29

Headline treatment: Generation capacity; not IT capacity

  1. DOE Paducah Site revitalized with data center campus

    NextEra Energy · Document date: 2026-07-29 · Supports

    https://www.investor.nexteraenergy.com/news-and-events/news-releases/2026/07-29-2026-133109921

Battery Storage · Up to 2.6 GW

planned nameplate · Paducah American Energy Hub (project)

Claim AST-B2-051 · Review: Approved · Claim date: 2026-07-29

Headline treatment: Generation capacity; not IT capacity

  1. DOE Paducah Site revitalized with data center campus

    NextEra Energy · Document date: 2026-07-29 · Supports

    https://www.investor.nexteraenergy.com/news-and-events/news-releases/2026/07-29-2026-133109921

First Operations Forecast · 2028-12-31

forecast · Paducah American Energy Hub (project)

Claim AST-B2-052 · Review: Approved With Followup · Claim date: 2026-07-29

  1. NextEra and Brookfield plan $100 billion Kentucky data center

    Reuters · Document date: 2026-07-29 · Supports

    https://www.reuters.com/business/energy/brookfield-nextera-develop-100-billion-data-center-campus-kentucky-source-says-2026-07-29/

Full Buildout Forecast · 2032-12-31

forecast · Paducah American Energy Hub (project)

Claim AST-B2-053 · Review: Approved With Followup · Claim date: 2026-07-29

  1. NextEra and Brookfield plan $100 billion Kentucky data center

    Reuters · Document date: 2026-07-29 · Supports

    https://www.reuters.com/business/energy/brookfield-nextera-develop-100-billion-data-center-campus-kentucky-source-says-2026-07-29/

Land Status · DOE land lease selection status

selected not executed · Paducah American Energy Hub (project)

Claim AST-B2-054 · Review: Approved · Claim date: 2026-07-29

  1. DOE Paducah Site revitalized with data center campus

    NextEra Energy · Document date: 2026-07-29 · Supports

    https://www.investor.nexteraenergy.com/news-and-events/news-releases/2026/07-29-2026-133109921

Existing Infrastructure · Transmission water fiber roads and land assets

site context · Paducah American Energy Hub (project)

Claim AST-B2-055 · Review: Approved · Claim date: 2026-07-29

  1. DOE Paducah Site revitalized with data center campus

    NextEra Energy · Document date: 2026-07-29 · Supports

    https://www.investor.nexteraenergy.com/news-and-events/news-releases/2026/07-29-2026-133109921

Definitive Agreements Status · Pending status

actual · Paducah American Energy Hub (project)

Claim AST-B2-056 · Review: Approved · Claim date: 2026-07-29

  1. DOE Paducah Site revitalized with data center campus

    NextEra Energy · Document date: 2026-07-29 · Supports

    https://www.investor.nexteraenergy.com/news-and-events/news-releases/2026/07-29-2026-133109921

Regulatory Status · Kentucky PSC oversight required status

planned · Paducah American Energy Hub (project)

Claim AST-B2-057 · Review: Approved · Claim date: 2026-07-29

  1. DOE Paducah Site revitalized with data center campus

    NextEra Energy · Document date: 2026-07-29 · Supports

    https://www.investor.nexteraenergy.com/news-and-events/news-releases/2026/07-29-2026-133109921

Counterparties and capital

U.S. Department of Energy · Landowner And Selection Authority · CMP-0675

Brookfield Asset Management · Prospective Lessee Developer Operator · CMP-0743

NextEra Energy · Prospective Generation And Storage Owner

Big Rivers Electric Corporation · Prospective Wholesale Supplier

Jackson Purchase Energy Cooperative · Prospective Retail Supplier

Paducah Power System · Community Supporter

Program Investment Plan

$100,000,000,000 · 2026-07-29

Financing record legacy-financing-AST-B2-047; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.