ODATA DC SP04 Osasco
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
On September 17, 2026, ODATA reported DeltaFlow liquid-cooling installation and testing underway at SP04 and QR03; this is not confirmation of completed commissioning or additional live MW. The announcement's US$630 million first-phase investment covers the two sites together, not SP04 alone. ODATA inaugurated operations at DC SP04 in Osasco in March 2025 and reported Phase 2 mobilisation in 2026. The 48 MW figure is a full-build facility plan, while Phase 2 is described as 24 MW.
Capacity
Full build IT capacity
Planned / design or future potential48 MW
Full build · Phase
Phase scope; not a whole-site figure
SourcePhase IT capacity
Planned / design or future potential24 MW
Phase 2 · Phase
Phase scope; not a whole-site figure
SourceRack density support
Planned / design or future potential50 kW per rack
Power density; not a whole-site capacity
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Opened 17 March 2025; commissioned IT load not disclosed.
Operator social update states 24 MW and seven generators.
Full facility envelope; no arithmetic Phase 1 allocation.
Milestones (2)
Mar 17, 2025 · Recorded actual event
Completed · Commercial operation
Source not linkedJun 18, 2026 · Recorded actual event
Completed · Construction started
Source not linkedParticipants
Owner
Sources by role
Owner (1)
- ODATA announces new data center in São Paulo, Brazil · Mar 17, 2025 · Primary
Operator
Sources by role
Operator (1)
- ODATA DC SP04 Phase 2 mobilisation update · Jun 18, 2026 · Corroborating
Operator (1)
- Prefeito participa da inauguração do Data Center ODATA em Osasco · Mar 18, 2025 · Corroborating
Operator (1)
- ODATA announces new data center in São Paulo, Brazil · Mar 17, 2025 · Primary
Other participants (1)
Government authority
Sources by role
Government authority (1)
- Prefeito participa da inauguração do Data Center ODATA em Osasco · Mar 18, 2025 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Investment commitment
$450mMar 17, 2025
Minimum amount because source says over USD 450M upon completion; no phase allocation.
Parties & sources
Aligned Data Centers (Sponsor / Parent company context) · ODATA (Sponsor)
Sources (1)
- ODATA announces new data center in São Paulo, Brazil · Mar 17, 2025
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (4)
Partially operational
48 MW
full build it capacity — 48 MW; partially operational future full build.
Under construction
24 MW
phase 2 it capacity — 24 MW; under construction.
Under construction
7 generator
phase 2 backup generation — 7 generator; under construction.
Partially operational
Delta3 cooling; operating and expanding.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.