Skip to content

ODATA DC SP04 Osasco

Rua Herman, Industrial Anhanguera, Osasco, São Paulo, BrazilPartially operational
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

On September 17, 2026, ODATA reported DeltaFlow liquid-cooling installation and testing underway at SP04 and QR03; this is not confirmation of completed commissioning or additional live MW. The announcement's US$630 million first-phase investment covers the two sites together, not SP04 alone. ODATA inaugurated operations at DC SP04 in Osasco in March 2025 and reported Phase 2 mobilisation in 2026. The 48 MW figure is a full-build facility plan, while Phase 2 is described as 24 MW.

Capacity

Full build IT capacity

Planned / design or future potential

48 MW

Full build · Phase

Phase scope; not a whole-site figure

Source

Phase IT capacity

Planned / design or future potential

24 MW

Phase 2 · Phase

Phase scope; not a whole-site figure

Source

Rack density support

Planned / design or future potential

50 kW per rack

Power density; not a whole-site capacity

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Initial operating facilityOperational

Opened 17 March 2025; commissioned IT load not disclosed.

Phase 2Under construction

Operator social update states 24 MW and seven generators.

Full buildPlanned

Full facility envelope; no arithmetic Phase 1 allocation.

Milestones (2)
SP04 operating inauguration

Mar 17, 2025 · Recorded actual event

Completed · Commercial operation

Source not linked
ODATA reports Phase 2 mobilisation

Jun 18, 2026 · Recorded actual event

Completed · Construction started

Source not linked

Participants

Aligned Data Centers

Owner

Sources by role
Owner (1)
ODATA

Operator

Sources by role
Operator (1)
Operator (1)
Operator (1)
Other participants (1)
Municipality of Osasco

Government authority

Sources by role
Government authority (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Investment upon completion

Transaction scope

$>450000000

Source

Financing records

Investment commitment

$450m

Mar 17, 2025

Minimum amount because source says over USD 450M upon completion; no phase allocation.

Parties & sources

Aligned Data Centers (Sponsor / Parent company context) · ODATA (Sponsor)

Site & development

Street location

Actual

Rua Herman, Industrial Anhanguera

Source

Technical specifications

Cooling platform

Design

Delta3

Source

Additional project facts

Project status

Actual

Partially operational

Source

Operating inauguration date

Actual

2025-03-17

Initial operating facility · Phase

Source

Backup generator count

Design

7 generator

Phase 2 · Phase

Source

Infrastructure & permits

Technical details (4)
Electric grid

Partially operational

48 MW

full build it capacity — 48 MW; partially operational future full build.

Electric grid

Under construction

24 MW

phase 2 it capacity — 24 MW; under construction.

Onsite generation

Under construction

7 generator

phase 2 backup generation — 7 generator; under construction.

Cooling system

Partially operational

Delta3 cooling; operating and expanding.

Public-source research. Plans may change. See Evidence for sources and qualifications.