Cartis diligence evidence schedule

NTT DATA Vienna 1 Data Center Campus

PRJ-0813 · Site · Vienna, Austria

Record last updated Oct 28, 2026

Scope and capacity

NTT DATA Vienna 1 Data Center Campus, also known as NTT Vienna 1, is a data center project in Vienna, Vienna, AT associated with NTT DATA. 8,500 square metres of server space and 15.4 MW maximum critical IT load. Vienna campus with onsite 20 MVA substation, VIX connectivity and dual 2N UPS systems.

Headline: 15.4 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · NTT Vienna 1 | Vienna | Vienna | AT

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 61124 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Vienna 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3382 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/vienna-1-data-center

Lifecycle status · Partially operational

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 61125 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Vienna 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3382 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/vienna-1-data-center

Reported capacity · 15.4 MW

Design · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 61126 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. NTT DATA NTT Vienna 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3382 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/vienna-1-data-center

Capacity basis · NTT DATA publishes 15.4 MW of critical IT capacity for this record boundary.

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 61127 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Vienna 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3382 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/vienna-1-data-center

Location context · NTT Vienna 1 | Vienna | Vienna | AT

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 101179 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Vienna 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3382 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/vienna-1-data-center

Lifecycle status · Partially operational

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 101180 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Vienna 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3382 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/vienna-1-data-center

Reported capacity · 15.4 MW

Planned / design or future potential · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 101181 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. NTT DATA NTT Vienna 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3382 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/vienna-1-data-center

Capacity basis · 15.4 MW facility or campus design capacity.

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 101182 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Vienna 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3382 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/vienna-1-data-center

Project identity · NTT Vienna 1

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 101184 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5653 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Location context · Vienna, Vienna, AT

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 101185 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5653 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Lifecycle status · Partially operational

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 101186 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5653 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Development detail · 8,500 Square metres of server space and 15.4 MW maximum critical IT load.

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 101187 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5653 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Capacity basis · 15.4 MW facility or campus design capacity.

Actual · NTT DATA Vienna 1 Data Center Campus (Project)

Claim 101188 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5653 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Counterparties and capital

NTT DATA · Developer · CMP-1100

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.