NTT DATA Jakarta 3 Data Center Campus

PRJ-0783 · Site · Bekasi, West Java, Indonesia

Record last updated Oct 28, 2026

Scope and capacity

NTT DATA Jakarta 3 Data Center Campus, also known as NTT Jakarta 3 Campus, is a data center project in Bekasi, West Java, ID associated with NTT DATA. Bekasi campus announced for 45 MW of critical IT load once fully developed. Jakarta-region hyperscale campus designed for carrier-neutral connectivity and phased expansion.

Headline: 45 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · NTT Jakarta 3 Campus | Bekasi | West Java | ID

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 61004 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT global data centers construction update

    NTT DATA · Document date: Jun 16, 2020 · Primary

    Source reference: SRC-3346 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/-/media/ntt/global/about-us/newsroom/global-data-centers-construction-update-press-release-jp.pdf

Lifecycle status · Partially operational

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 61005 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT global data centers construction update

    NTT DATA · Document date: Jun 16, 2020 · Primary

    Source reference: SRC-3346 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/-/media/ntt/global/about-us/newsroom/global-data-centers-construction-update-press-release-jp.pdf

Reported capacity · 45 MW

Design · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 61006 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. NTT global data centers construction update

    NTT DATA · Document date: Jun 16, 2020 · Primary

    Source reference: SRC-3346 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/-/media/ntt/global/about-us/newsroom/global-data-centers-construction-update-press-release-jp.pdf

Capacity basis · NTT DATA publishes 45 MW of critical IT capacity for this record boundary.

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 61007 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT global data centers construction update

    NTT DATA · Document date: Jun 16, 2020 · Primary

    Source reference: SRC-3346 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/-/media/ntt/global/about-us/newsroom/global-data-centers-construction-update-press-release-jp.pdf

Location context · NTT Jakarta 3 Campus | Bekasi | West Java | ID

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 100896 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT global data centers construction update

    NTT DATA · Document date: Jun 16, 2020 · Primary

    Source reference: SRC-3346 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/-/media/ntt/global/about-us/newsroom/global-data-centers-construction-update-press-release-jp.pdf

Lifecycle status · Partially operational

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 100897 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT global data centers construction update

    NTT DATA · Document date: Jun 16, 2020 · Primary

    Source reference: SRC-3346 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/-/media/ntt/global/about-us/newsroom/global-data-centers-construction-update-press-release-jp.pdf

Reported capacity · 45 MW

Planned / design or future potential · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 100898 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. NTT global data centers construction update

    NTT DATA · Document date: Jun 16, 2020 · Primary

    Source reference: SRC-3346 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/-/media/ntt/global/about-us/newsroom/global-data-centers-construction-update-press-release-jp.pdf

Capacity basis · 45 MW facility or campus design capacity.

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 100899 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT global data centers construction update

    NTT DATA · Document date: Jun 16, 2020 · Primary

    Source reference: SRC-3346 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/-/media/ntt/global/about-us/newsroom/global-data-centers-construction-update-press-release-jp.pdf

Project identity · NTT Jakarta 3 Campus

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 100901 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5571 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Location context · Bekasi, West Java, ID

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 100902 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5571 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Lifecycle status · Partially operational

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 100903 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5571 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Development detail · Bekasi campus announced for 45 MW of critical IT load once fully developed.

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 100904 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5571 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Capacity basis · 45 MW facility or campus design capacity.

Actual · NTT DATA Jakarta 3 Data Center Campus (Project)

Claim 100905 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5571 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Counterparties and capital

NTT DATA · Developer · CMP-1100

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.