NTT DATA Amsterdam 1 Data Center Campus
- Planned critical IT
- 40 MW
- Updated
- Oct 28, 2026
NTT DATA Amsterdam 1 Data Center Campus, also known as NTT Amsterdam 1, is a data center project in Rozenburg, North Holland, NL associated with NTT DATA. 20.7 MW current critical IT load; 40 MW once fully built out; 17,200 square metres at full build. Schiphol-Rijk campus with dual onsite substations, carrier-neutral connectivity and free-cooling systems. 20.7 MW is NTT DATA’s current critical IT design; 40 MW is the full-build campus envelope.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
20.7 MW is NTT DATA’s current critical IT design; 40 MW is the full-build campus envelope.
Participants
Developer
Sources by role
Developer (1)
- NTT DATA NTT Amsterdam 1 profile · Aug 27, 2026 · Primary
Site & development
Additional project facts
Infrastructure & permits
Technical details (2)
Energized
Schiphol-Rijk campus with dual onsite substations, carrier-neutral connectivity and free-cooling systems.
Operational
Cooling and efficiency claims remain limited to operator-described designs; no water use or delivered load is inferred.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.