Skip to content
← Return to profile

Cartis diligence evidence schedule

NEXTDC S7 Sydney

PRJ-0257 · Site · Eastern Creek / Blacktown, New South Wales, Australia

Captured 2026-09-06T04:12:23.922Z · Record last updated 2026-08-25

SHA-256: b0a19dc6a82f8a2e36a9cf6954843b09b0213f8f44142c95cc77d6beea57b6a9

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Single Eastern Creek campus in State Significant Development review; distinct from S4 and not yet approved or operating. NEXTDC S7 Sydney is in Eastern Creek / Blacktown, NSW, AU and is a data center campus with preconstruction status.

Headline: 550 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Site Purchase Price · 353 AUD millions

Source report · NEXTDC S7 Sydney (project)

Claim 23781 · Review: Approved · Claim date: 2024-10-17T00:00:00+00:00

  1. OpenAI's Australian data centre drops water recycling plan

    Reuters · Document date: 2026-07-22 · Corroborating

    https://www.reuters.com/business/energy/openais-australian-data-centre-drops-water-recycling-plan-testing-drive-curb-2026-07-22/
  2. S7 Pre-Development Application PDA-107168706

    NSW Department of Planning, Housing and Infrastructure · Document date: 2026-04-09 · Corroborating

    https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=PDA-107168706%2120260409T040422.778+GMT
  3. Building the next generation of sovereign AI infrastructure in Australia

    NEXTDC · Document date: 2025-12-05 · Corroborating

    https://www.nextdc.com/news/building-the-next-generation-of-sovereign-ai-infrastructure-in-australia
  4. NEXTDC inks MoU with OpenAI to develop AI infrastructure

    Reuters · Document date: 2025-12-04 · Corroborating

    https://www.reuters.com/world/asia-pacific/australias-nextdc-signs-deal-with-openai-build-hyperscale-ai-campus-gpu-2025-12-04/
  5. NEXTDC announces acquisition of S7 site

    NEXTDC · Document date: 2024-10-17 · Primary

    https://www.nextdc.com/news/nextdc-acquires-new-sydney-data-centre-s7
  6. ASX Release — S7 Development 550MW

    NEXTDC · Document date: 2024-10-17 · Corroborating

    https://announcements.asx.com.au/asxpdf/20241017/pdf/0696y1n074lfkz.pdf
  7. NEXTDC S7 Data Centre, Eastern Creek

    NSW Planning Portal · Document date: Not published · Corroborating

    https://www.planningportal.nsw.gov.au/major-projects/projects/nextdc-s7-data-centre-eastern-creek
  8. S7 Sydney Data Centre — In Planning

    NEXTDC · Document date: Not published · Corroborating

    https://www.nextdc.com/data-centres/sydney-data-centres/s7-sydney

Developable Site Area Announcement · 258,000 square metres

Source report · NEXTDC S7 Sydney (project)

Claim 23782 · Review: Approved · Claim date: Not published

  1. NEXTDC announces acquisition of S7 site

    NEXTDC · Document date: 2024-10-17 · Primary

    https://www.nextdc.com/news/nextdc-acquires-new-sydney-data-centre-s7
  2. ASX Release — S7 Development 550MW

    NEXTDC · Document date: 2024-10-17 · Corroborating

    https://announcements.asx.com.au/asxpdf/20241017/pdf/0696y1n074lfkz.pdf

Site Area Planning · 255,157 square metres

Source report · NEXTDC S7 Sydney (project)

Claim 23783 · Review: Approved · Claim date: Not published

  1. S7 Pre-Development Application PDA-107168706

    NSW Department of Planning, Housing and Infrastructure · Document date: 2026-04-09 · Primary

    https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=PDA-107168706%2120260409T040422.778+GMT

Marketed It Capacity · 550 MW+

Planned / design or future potential · NEXTDC S7 Sydney (project)

Claim 23784 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. NEXTDC announces acquisition of S7 site

    NEXTDC · Document date: 2024-10-17 · Primary

    https://www.nextdc.com/news/nextdc-acquires-new-sydney-data-centre-s7
  2. S7 Sydney Data Centre — In Planning

    NEXTDC · Document date: Not published · Corroborating

    https://www.nextdc.com/data-centres/sydney-data-centres/s7-sydney

Planning Building Count · 3

Source report · NEXTDC S7 Sydney (project)

Claim 23786 · Review: Approved · Claim date: Not published

  1. S7 Pre-Development Application PDA-107168706

    NSW Department of Planning, Housing and Infrastructure · Document date: 2026-04-09 · Corroborating

    https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=PDA-107168706%2120260409T040422.778+GMT
  2. NEXTDC S7 Data Centre, Eastern Creek

    NSW Planning Portal · Document date: Not published · Primary

    https://www.planningportal.nsw.gov.au/major-projects/projects/nextdc-s7-data-centre-eastern-creek

Backup Generator Count · 340 generators

Source report · NEXTDC S7 Sydney (project)

Claim 23787 · Review: Approved · Claim date: Not published

  1. NEXTDC S7 Data Centre, Eastern Creek

    NSW Planning Portal · Document date: Not published · Primary

    https://www.planningportal.nsw.gov.au/major-projects/projects/nextdc-s7-data-centre-eastern-creek

Estimated Development Cost · 7,154.56 AUD millions

Source report · NEXTDC S7 Sydney (project)

Claim 23788 · Review: Approved · Claim date: Not published

  1. S7 Pre-Development Application PDA-107168706

    NSW Department of Planning, Housing and Infrastructure · Document date: 2026-04-09 · Primary

    https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=PDA-107168706%2120260409T040422.778+GMT

Construction Jobs · 2,000 jobs

Source report · NEXTDC S7 Sydney (project)

Claim 23789 · Review: Approved · Claim date: Not published

  1. S7 Pre-Development Application PDA-107168706

    NSW Department of Planning, Housing and Infrastructure · Document date: 2026-04-09 · Primary

    https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=PDA-107168706%2120260409T040422.778+GMT

Operational Jobs · 425 jobs

Source report · NEXTDC S7 Sydney (project)

Claim 23790 · Review: Approved · Claim date: Not published

  1. S7 Pre-Development Application PDA-107168706

    NSW Department of Planning, Housing and Infrastructure · Document date: 2026-04-09 · Primary

    https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=PDA-107168706%2120260409T040422.778+GMT

First Phase Target · H2 2027

Planned / design or future potential · NEXTDC S7 Sydney (project)

Claim 23792 · Review: Approved · Claim date: Not published

  1. Building the next generation of sovereign AI infrastructure in Australia

    NEXTDC · Document date: 2025-12-05 · Primary

    https://www.nextdc.com/news/building-the-next-generation-of-sovereign-ai-infrastructure-in-australia

Cooling Design Initial · Closed loop high density liquid cooling without ongoing potable water

Source report · NEXTDC S7 Sydney (project)

Claim 23793 · Review: Approved · Claim date: Not published

  1. Building the next generation of sovereign AI infrastructure in Australia

    NEXTDC · Document date: 2025-12-05 · Primary

    https://www.nextdc.com/news/building-the-next-generation-of-sovereign-ai-infrastructure-in-australia

Cooling Design Current · Closed loop chip liquid cooling with waterless fan heat rejection

Source report · NEXTDC S7 Sydney (project)

Claim 23794 · Review: Approved · Claim date: Not published

  1. OpenAI's Australian data centre drops water recycling plan

    Reuters · Document date: 2026-07-22 · Primary

    https://www.reuters.com/business/energy/openais-australian-data-centre-drops-water-recycling-plan-testing-drive-curb-2026-07-22/

Ssd Status · Prepare EIS

Source report · NEXTDC S7 Sydney (project)

Claim 23795 · Review: Approved · Claim date: Not published

  1. NEXTDC S7 Data Centre, Eastern Creek

    NSW Planning Portal · Document date: Not published · Primary

    https://www.planningportal.nsw.gov.au/major-projects/projects/nextdc-s7-data-centre-eastern-creek

Counterparties and capital

Blacktown City Council · Government Authority · CMP-0133

NEXTDC Limited · Developer · CMP-0157

NSW Department of Planning, Housing and Infrastructure · Government Authority · CMP-0132

Sydney Water · Utility Provider · CMP-0690

Transgrid · Utility Provider · CMP-0689

Urbis Ltd · Contractor · CMP-0688

Land Acquisition Consideration

A$353,000,000 · 2024-10-17

Approximate purchase price before taxes and transaction costs, with progressive parcel settlement across FY25. This is an acquisition transaction, not construction financing or total project cost.

NEXTDC Limited (Other)

Financing record 67; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.